A weekly schedule tracking testing, defects, and enhancements for the 4.5 release. This weekly schedule is derived from the
detailed schedule.
Legend
Keyword | Meaning |
SLIPPED | This work item has not been completed in the past week. |
SLIPPED <n> | This work item has not been completed in the past 'n' weeks. |
COMPLETE | This work item has been completed. |
10/03/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
10/10/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
10/17/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
10/24/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
10/31/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
11/07/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
11/14/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
- EMMA status update.
- Test Automation status update.
- EclipseCon 2008 update.
- Review enhancement 208110.
- Review enhancement 162605.
- Review enhancement 166025.
- Design enhancement 202695.
|
|
|
11/21/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
- Code review 208719 and check in.
- Code review 208720 and check in.
- Since 208721 wasn't finished yet, continue work on.
- Code review 208722 and check in.
- Code review 207240 and check in.
- Review work on 207251.
- Since 207253 wasn't finished, continue tracking progress.
- Finish 206665, since it couldn't be contained last week.
- Track completion of 208586
- Track completion of 209057
- Provide patch for 207763.
- Provide patch for 207806.
- Code review 194954 and check in.
- Code review 206718 and check in.
- Start work on 205821.
- Start work on 167036.
|
- EclipseCon 2008 update.
- Review enhancement 208110.
- Review enhancement 162605.
- Review enhancement 166025.
- Implement enhancement 202695.
|
|
|
11/28/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
- Design 200251.
- Design 148629.
- Begin JSSE/JNI security integration 206878.
- Update automated testcases for ProbeKit that were affected by a change to the base eclipse UI menu items.
- Implement 199601.
- Implement 208762.
- Initial investigation of profiling problems on Solaris reported during TPTP Webinar.
- Nominate Mohammed Mostafa as a committer contributing to Static Analysis.
|
|
- EMMA status update.
- Test Automation status update.
- EclipseCon 2008 update.
- Design enhancement 208110.
- Review enhancement 162605.
- Review enhancement 166025.
- Implement enhancement 202695.
- Complete defect 187864.
- Complete defect 164835.
- Complete defect 209263.
- Fix defect 208616.
- Fix defect 170652.
|
|
|
12/05/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
- Issues found during review of 208721, address all open issues.
- During review found that 208722 is only 75% completed , need to address open issues.
- Keep track of second part of 207251.
- Keep track of 207253, currently blocked by some AGR defects though.
- Continue tracking 167036.
- Continue work on 210476, 210479.
- Track completion of 194030, 195026, 206499.
- Track completion of 164039, 176653.
- Clean-up test suites in preparation for test pass.
- Automate 50% of manual test suites.
- Fix defect 208586.
- Complete 207240 - build integration and smoke testing.
- Continue tracking 205821.
|
- COMPLETE Test Automation status update.
- COMPLETE Review EclipseCon 2008 tutorial, long talk, and short talk submissions.
- COMPLETE Clean-up test suites in preparation for test pass.
- COMPLETE Automate 50% of manual test suites.
- SLIPPED Resolve EMMA issue #1 and #2.
- COMPLETE Design enhancement 162605.
- SLIPPED Design enhancement 166025.
- COMPLETE Implement enhancement 202695.
- COMPLETE Complete defect 208616.
- SLIPPED Complete defect 186148.
- SLIPPED Complete defect 210744.
- SLIPPED Complete defect 210742.
- COMPLETE Complete defect 190558.
- COMPLETE Complete defect 193543.
- COMPLETE Complete defect 179037.
- SLIPPED Complete defect 107432.
- COMPLETE Fix defect 170652.
- COMPLETE Fix defect 207777.
- COMPLETE Fix defect 210576.
- COMPLETE Fix defect 170656.
- COMPLETE Fix defect 171083.
- COMPLETE Fix defect 170654.
- COMPLETE Fix defect 211066.
- COMPLETE Fix defect 208583.
- COMPLETE Fix defect 170653.
- COMPLETE Fix defect 165140.
- COMPLETE Fix defect 145070.
- COMPLETE Fix defect 151919.
- COMPLETE Fix defect 201849.
- COMPLETE Track defect 210955 (depends on BIRT defect 210968).
|
- Clean-up test suites in preparation for test pass.
- Automate 50% of manual test suites.
|
|
12/12/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
- SLIPPED 2 Resolve EMMA issue #1 and #2.
- SLIPPED 2 Design enhancement 166025.
- SLIPPED 2 Complete defect 186148.
- SLIPPED Resolve EMMA issue #3.
- SLIPPED Present Test Automation to TPTP (e.g. AG call).
- SLIPPED Present EMMA to TPTP (e.g. AG call).
- SLIPPED Implement enhancement 202695.
- SLIPPED Complete defect 210742.
- SLIPPED Complete defect 170656.
- SLIPPED Complete defect 171083.
- SLIPPED Complete defect 170654.
- SLIPPED Complete defect 211066.
- SLIPPED Complete defect 151919.
- SLIPPED Complete defect 145070.
- COMPLETE Complete defect 210744.
- COMPLETE Complete defect 107432.
- COMPLETE Complete defect 170652.
- COMPLETE Complete defect 207777.
- COMPLETE Complete defect 210576.
- COMPLETE Complete defect 208583.
- COMPLETE Complete defect 170653.
- COMPLETE Complete defect 165140.
- COMPLETE Complete defect 201849.
- COMPLETE Complete defect 212393.
- COMPLETE Complete defect 212535.
- COMPLETE Complete defect 212041.
- COMPLETE Resolve defect 210955 (depends on BIRT defect 210968).
- COMPLETE Complete component reorganization.
- COMPLETE Final EclipseCon 2008 tutorial, long talk, and short talk submissions.
- COMPLETE Design enhancement 162605.
- COMPLETE 4.5 I4 TP1
- Fix defect 212762.
- Fix defect 212564.
- Fix defect 212580.
|
|
- 4.5 I4 Development
- 4.5 I4 TP1
|
12/19/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
- SLIPPED 3 Design enhancement 166025.
- SLIPPED 3 Complete defect 186148.
- SLIPPED 3 Resolve EMMA issue #1 and #2.
- SLIPPED 2 Resolve EMMA issue #3.
- SLIPPED 2 Present Test Automation to TPTP (e.g. AG call).
- SLIPPED 2 Present EMMA to TPTP (e.g. AG call).
- SLIPPED 2 Implement enhancement 202695.
- SLIPPED 2 Complete defect 210742.
- SLIPPED 2 Complete defect 170656.
- SLIPPED 2 Complete defect 171083.
- SLIPPED 2 Complete defect 170654.
- SLIPPED 2 Complete defect 211066.
- SLIPPED 2 Complete defect 151919.
- SLIPPED 2 Complete defect 145070.
- SLIPPED Web site update (defect 210250).
- SLIPPED Complete defect 212564.
- SLIPPED Complete defect 212580.
- COMPLETE 4.5 I4 TP1
- COMPLETE Implement enhancement 202695.
- COMPLETE Complete defect 212762.
|
|
|
12/26/2007
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
- Christmas break.
- Design 148629.
|
|
|
|
|
01/02/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
- SLIPPED 4 Design enhancement 166025.
- SLIPPED 4 Complete defect 186148.
- SLIPPED 4 Resolve EMMA issue #1 and #2.
- SLIPPED 3 Resolve EMMA issue #3.
- SLIPPED 3 Present Test Automation to TPTP (e.g. AG call).
- SLIPPED 3 Present EMMA to TPTP (e.g. AG call).
- SLIPPED 3 Implement enhancement 202695.
- SLIPPED 3 Complete defect 210742.
- SLIPPED 3 Complete defect 170656.
- SLIPPED 3 Complete defect 170654.
- SLIPPED 3 Complete defect 211066.
- SLIPPED 3 Complete defect 151919.
- SLIPPED 3 Complete defect 145070.
- SLIPPED 2 Web site update (defect 210250).
- COMPLETE Complete defect 171083.
- COMPLETE Complete defect 212564.
- COMPLETE Complete defect 212580.
- COMPLETE 4.5 I4 TP2
- COMPLETE Implement enhancement 202695.
|
|
- Fix any blocking issues from 4.5 I4 TP1
- 4.5 I4 TP2
|
01/09/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
- SLIPPED Complete 208721
- SLIPPED Complete 208723
- SLIPPED Complete 208725
- SLIPPED Complete 208726
- SLIPPED Complete 208733
- Check in fixes for 212792,
207160,
207763,
207806,
167036,
206499
- START work on 212806
- START work on 185625
- Complete 213384
- Complete 194030
- Complete 204471
- Complete 206205
- Attempt completing bugs 164039,
205274,
166918,
185959,
133122,
206511
|
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- 4.5 I4 TP2
- 4.5 I5 Development
|
01/16/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
01/23/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
- Complete bugs 164039,
212807,
199417
- Complete bug 208679, bug 182872, bug 148272, bug 184530, bug 192250, bug 201975, bug 154861, bug 181285, bug 104281
- SLIPPED complete bug 212806
- Attempt complete bug 180950, bug 181090, bug 201936, bug 153615, bug 166543
- Web site update (defect 210250).
|
|
|
|
01/30/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
- 4.4.1 test pass
- SLIPPED complete bugs 164039,
212807,
199417
- SLIPPED complete bug 208679, bug 182872, bug 148272, bug 184530, bug 192250
- SLIPPED complete bug 212806, most likely not containable in i5
- Attempt complete bug 180950, bug 181090, bug 201936, bug 153615, bug 166543
|
|
|
- 4.5 I5 Development
- 4.4.1 TP1
|
02/06/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
02/13/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
- 4.4.1 TP1
- Fix any blocking issues from 4.4.1 TP1
- 4.5 I5 TP1
|
02/20/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
- Complete 216790.
- Complete 218546.
- Complete 217708.
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- SLIPPED Define the test and defect plan for this iteration.
- COMPLETE 4.5 I5 TP1
- COMPLETE Test enhancement 166025.
- COMPLETE Clean-up Bugzilla versions/targets.
- COMPLETE Complete bug 218868
- COMPLETE Complete bug 218843
- COMPLETE Complete bug 219338
- COMPLETE Complete bug 201150
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- 4.5 I5 TP1
- 4.5 I6 Development
|
02/27/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
03/05/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
03/12/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
03/19/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
03/26/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
04/02/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
04/09/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- 4.5 I6 TP2
- 4.5 I7 Development
|
04/16/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
04/23/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
- Web site update (defect 210250).
|
|
- Web site update (defect 210250).
|
- Web site update (defect 210250).
|
- 4.5 I7 Development
- 4.5 I7 TP1
|
04/30/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
05/07/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- Define the test and defect plan for this iteration.
- Clean-up Bugzilla versions/targets.
|
- 4.5 I7 TP2
- 4.5 I8 Development
|
05/14/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
- 4.5 I8 Development
- 4.5 I8 TP1
|
05/21/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
05/28/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
- 4.5 I8 TP1
- Fix any blocking issues from 4.5 I8 TP1
|
06/04/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
- Fix any blocking issues from 4.5 I8 TP1
- 4.5 I8 TP2
|
06/11/2008
Platform Project | Monitoring Project | Test Project | Trace Project | Notes |
|
|
|
|
|
chris_test_page