Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
DTP PMC and Project Lead Meeting: October 1, 2007
Revision as of 14:32, 1 October 2007 by Unnamed Poltroon (Talk)
← Back to DTP PMC and Project Lead Meeting page
Contents
Attendees
- John Graham
- Sheila Sholars
- Brian Fitzpatrick
- Linda Chan
Regrets
Agenda
- DTP 1.5.1 was released on Thursday, 9/27
- 94 bugs resolved
- 34 builds
- 3 months of work (June 29 --> September 26)
- Last minute heart attack award goes to SQL Dev for bug 204632
- No meeting next week: Eclipse Summit Europe, M --> F
- Builds on a "best faith" effort during the week, depending on internet connection
- Builds for DTP 1.5.2 start today, 10/1, when bugs are resolved (as we did in 1.5.1)
- Review project plans