This page lays out milestone plans for the development of Equinox p2 in the Eclipse Galileo release (aka the Eclipse Platform version 3.5).


Current Milestone Plan: M4 - December 12th, 2008

  • Progress.gif Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency [DJ] (Note: impact on other SDK components)
  • Map out metadata authoring and development work flow [Andrew N] (Note: impact on PDE tooling work)
  • Investigate install handler replacement solution [helpwanted]
  • Progress.gif Complete integration of publisher with PDE build [Andrew N]
  • Repository association feature work [John]
  • Support for composite repository [Andrew C.]
  • Closer integration with VM [Simon/Pascal]
  • Polish the action contribution model [Simon]
  • Metadata constructs allowing the expression of negation and choice [Pascal]
  • Complete integration of install view with about dialog [Susan]
  • Complete detailed drill-down of IU's in install view and update/install wizards [Susan]
  • Investigate fast-path install scenarios [Susan]
  • Add regression/performance tests

Future Plans

M5 - January 30th, 2009 - Major Feature Freeze

  • Complete implementation of install handler replacement
  • Complete implementation for fast-path install scenarios Bug 223264 [Susan]
  • Complete implementation for available view affordances Bug 216032 [Susan]
  • investigate streamlined license UI Bug 217944 [Susan]
  • investigate better presentation of repositories [Susan]
  • Add regression/performance tests

M6 - March 12th, 2009 - API Freeze

  • Polish API javadoc, package.html doc
  • Add regression/performance tests

M7 - May 1st, 2009 - Development Complete

  • Polish items
  • Performance work
  • Testing and test framework improvements
  • Release train build/repository assistance

Previous Plans

M1 - August 8th, 2008

  • Decompression
  • Bug triage, community assistance
  • Fixing critical defects and performance problems
  • Test framework for dropin reconciler [DJ]
  • Creation of Publisher - replacement for metadata generator [Jeff]
  • UI walkthrough and usability input [Susan]

M2 - September 19th, 2008

  • Planning
  • Ok green.gifFocus on 3.4.1 defects
  • Ok green.gifPort 3.4.1 fixes to 3.5 stream
  • Ok green.gifIntegration of publisher [Jeff]
  • Ok green.gifMock up new UI workflows for community feedback [Susan]
  • Ok green.gifAdd a bunch of automated tests.

M3 - October 31, 2008

  • Ok green.gif Convert from using URL to URI where possible [John]
  • Ok green.gif Refactor repository managers to remove code duplication [John]
  • Ok green.gif Revise Touchpoint action contribution model [Simon]
  • Progress.gif Integration of publisher with PDE build [Andrew N]
    • Rewrite generator app and Ant tasks to invoke publisher.
    • To be continued in M4
  • Ok green.gif Investigate use of Apache HTTP client (Note: cross-project impact on ECF) [Scott]
  • Ok green.gif MD5 processing step to verify download integrity [Pascal]
  • Progress.gif Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency [DJ] (Note: impact on other SDK components)
    • To be continued in M4
  • Map out metadata authoring and development work flow [Andrew N] (Note: impact on PDE tooling work)
    • Deferred to M4
  • Investigate install handler replacement solution [helpwanted]
    • Deferred to M4
  • Glass.gif Investigate metadata construct to separate line-up information from grouping information [Pascal]
    • Dropped until further notice
  • Ok green.gif Reorganize UI workflows to separate update from install [Susan] (Note: potential impact on Platform UI)
  • Ok green.gif Investigate drill-down of install info and impact on metadata [Susan]
  • Ok green.gif Release reconciler test framework [DJ]
  • Ok green.gif Release publisher tests [John]

Past Releases

p2 Ganymede Milestone Plan

Legend

Glass.gif Needs some investigation

Progress.gif Work in progress

Ok green.gif Bug fixed / Feature added