This page lays out milestone plans for the development of Equinox p2 in the Eclipse Galileo release (aka the Eclipse Platform version 3.5).
- For a high level feature plan, see Equinox/p2/Galileo/Features.
- For a more detailed view of the UI plan, see Equinox p2 UI Plan.
Contents
Current Milestone Plan: M5 - January 30th, 2009 - Major Feature Freeze
- Complete implementation of install handler replacement [Henrik]
- Improve available view affordances Bug 216032 [Susan]
- Better presentation of repositories Bug 250316 [Susan]
- Improve the revert experience and workflow Bug 216031 [Simon / Susan]
- Investigate streamlined license UI Bug 217944 [Susan]
- Investigate fast-path install scenarios Bug 223264 [Susan]
- Complete integration of publisher with PDE build [Andrew N / Jeff]
- Multiple processes modifying the same profile registry / profile [Pradeep]
- Need a way to ensure that a bundle pool is only used by one agent to avoid problems with GC [Pradeep]
- Support for explanation [Jed / Daniel / Pascal]
- Add regression/performance tests
Future Plans
3.5 items left
- Misc
- Review the support for UNC paths [1]
- Transport
- Better explanation of error
- Improved cancellability
- Artifact repository
- Robustness in reading and writing.
- Mirroring application... ppl still have problems
- Concurrency issues when reading and writing (one process)
- Eclipse touchpoint
- Framework extensions
- Improve detection for conflicting arguments
- Native touchpoint
- Improve detection for conflicting arguments
- Engine
- Reacting to change of CU
- Reacting to change of property
- GC of profile registry
- Update manager
- Provide replacement constructs for UM
M6 - March 12th, 2009 - API Freeze
- Polish API javadoc, package.html doc
- Add regression/performance tests
M7 - May 1st, 2009 - Development Complete
- Polish items
- Performance work
- Testing and test framework improvements
- Release train build/repository assistance
Previous Plans
M1 - August 8th, 2008
- Decompression
- Bug triage, community assistance
- Fixing critical defects and performance problems
- Test framework for dropin reconciler [DJ]
- Creation of Publisher - replacement for metadata generator [Jeff]
- UI walkthrough and usability input [Susan]
M2 - September 19th, 2008
- Planning
- Focus on 3.4.1 defects
- Port 3.4.1 fixes to 3.5 stream
- Integration of publisher [Jeff]
- Mock up new UI workflows for community feedback [Susan]
- Add a bunch of automated tests.
M3 - October 31, 2008
- Convert from using URL to URI where possible [John]
- Refactor repository managers to remove code duplication [John]
- Revise Touchpoint action contribution model [Simon]
- Integration of publisher with PDE build [Andrew N]
- Rewrite generator app and Ant tasks to invoke publisher.
- To be continued in M4
- Investigate use of Apache HTTP client (Note: cross-project impact on ECF) [Scott]
- MD5 processing step to verify download integrity [Pascal]
- Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency [DJ] (Note: impact on other SDK components)
- To be continued in M4
- Map out metadata authoring and development work flow [Andrew N] (Note: impact on PDE tooling work)
- Deferred to M4
- Investigate install handler replacement solution [helpwanted]
- Deferred to M4
- Investigate metadata construct to separate line-up information from grouping information [Pascal]
- Dropped until further notice
- Reorganize UI workflows to separate update from install [Susan] (Note: potential impact on Platform UI)
- Investigate drill-down of install info and impact on metadata [Susan]
- Release reconciler test framework [DJ]
- Release publisher tests [John]
M4 - December 12th, 2008
- Identify all Eclipse SDK dependencies on Update Manager and determine work required to remove Update Manager dependency [DJ] (Note: impact on other SDK components)
- Map out metadata authoring and development work flow [Andrew N] (Note: impact on PDE tooling work)
- Investigate install handler replacement solution [helpwanted]
- Moved to M5. Help needed.
- Complete integration of publisher with PDE build [Andrew N]
- To be continued in M5. Help needed.
- Repository association feature work [John]
- Support for composite repository [Andrew C.]
- Closer integration with VM [Simon/Pascal]
- Removed from Galileo unless someone picks it up
- Polish the action contribution model [Simon]
- Metadata constructs allowing the expression of negation and choice [Pascal]
- Removed from Galileo, unless someone picks it up.
- Complete integration of install view with about dialog [Susan]
- Complete detailed drill-down of IU's in install view and update/install wizards [Susan]
- Separation of UI contributions from the supporting class library [Susan]
- Investigate fast-path install scenarios [Susan]
- Moved to M5
- Add regression/performance tests