Skip to main content

Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "COSMOS Document Schedule"

(COSMOS Document Schedule for GA)
(COSMOS Document Schedule for GA)
Line 31: Line 31:
 
|-
 
|-
  
! header 1
+
! Activity
 +
! Duration
  
! header 2
+
! Projected Date
  
! header 3
 
  
 
|-
 
|-
  
| row 1, cell 1
+
| First draft
 +
| n/a
 +
| 03/12/08
 +
|-
 +
| First review
 +
| 5 days
 +
| 03/19/08
  
| row 1, cell 2
+
|-
  
| row 1, cell 3
+
| Second draft
 +
 +
| 04/09/08
 +
|-
 +
| Second review
 +
| 5 days
 +
| o4/16/08
  
 
|-
 
|-
  
| row 2, cell 1
+
| Final edited draft
 +
 +
| 05/21/08
  
| row 2, cell 2
+
| Approval version
 +
| n/a
 +
| 06/02/08
 +
|-
 +
| HTML Helps version
 +
| 5 days
 +
| 06/04/08
  
| row 2, cell 3
 
  
 
|}
 
|}

Revision as of 22:29, 30 January 2008

COSMOS Wiki > COSMOS Document Plan


Documents

There will be two documents:

  • COSMOS User's Guide
  • COSMOS Developer's Guide

Availablility

  • Documents available two weeks before GA

Milestones

The development of a document consists the following chronological milestones.

  1. First draft
  2. Review
  3. Second draft
  4. Review
  5. Final version distributed to reviewers
  6. Approval
  7. Create PDF and online helps
  8. Test online helps

COSMOS Document Schedule for GA

Activity Duration Projected Date


First draft n/a 03/12/08
First review 5 days 03/19/08
Second draft 04/09/08
Second review 5 days o4/16/08
Final edited draft 05/21/08 Approval version n/a 06/02/08
HTML Helps version 5 days 06/04/08