COSMOS Wiki > COSMOS Document Plan


Documents

There will be two documents:

  • COSMOS User's Guide
  • COSMOS Developer's Guide

Availablility

  • Documents available two weeks before GA

Milestones

The development of a document consists the following chronological milestones.

  1. First draft
  2. Review
  3. Second draft
  4. Review
  5. Final version distributed to reviewers
  6. Approval
  7. Create PDF and online helps
  8. Test online helps

COSMOS Document Schedule for GA

header 1 header 2 header 3
row 1, cell 1 row 1, cell 2 row 1, cell 3
row 2, cell 1 row 2, cell 2 row 2, cell 3

Back to the top