Below is a list of the proposed milestone dates for each action
Task | Due Date | |
---|---|---|
Analysis of EPs and Plugins Model | 26/Nov/2007 | |
EclipseME Evaluation | 10/Dec/2007 | |
User Experience Review | 21/Dec/2007 | Includes the decision on "Balance" between Product or Framework. |
Proposed Architecture | 14/Jan/2008 |
By the end of this year, collect prioritized. Use-cases by Mid January.