Difference between revisions of "Callisto Plan Summary"
(added link to final daze schedule) |
|||
Line 7: | Line 7: | ||
update this page to reflect current status and plans. | update this page to reflect current status and plans. | ||
− | See also [Callisto Final Daze] | + | See also [[Callisto Final Daze]] |
=== Everything In A Table === | === Everything In A Table === |
Revision as of 22:10, 17 June 2006
This is summary table of the Callisto Plan
The primary purpose of this summary is to provide one place to see the correlations of the Callisto release candiate names and dates and the participating projects release candidate names and dates. The participating projects may update this page to reflect current status and plans.
See also Callisto Final Daze
Contents
Everything In A Table
Callisto | ||||||||
RC1a | RC2 | RC3 | RC4 | RC5 | RC6 | GA | ||
BIRT | RC0 | RC2 | RC3a | RC4 | RC5 | RC6 | ||
CDT | RC0 | RC1 | RC2 | RC3 | ||||
DTP | RC1 | RC2 | RC3 | RC4 | RC5 | |||
EMF | RC1 | RC2a | RC4 | RC6 | RC7 | |||
GEF | RC0 | RC2 | RC3 | RC4 | RC5 | |||
GMF | RC0 | RC2 | RC3 | RC4 | RC5 | RC6 | ||
Platform | RC1a | RC2 | RC4 | RC6 | RC7 | last M-build | ||
TPTP | i2 | RC2 | i3 | RC5 | RC6 | |||
WTP | RC1a | RC2 | RC3 | RC4 | RC5 | RC6 | ||
VE | M3 | RC1 | RC2 |
RC1a (25-Apr)
- 14-Apr - Platform (RC1a)
- 19-Apr - CDT, DTP(RC1), EMF (RC1) , GEF (RC0), VE (M3)
- 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
- 25-Apr - admin, mirror propagation
RC2 (9-May)
- 28-Apr - Platform (RC2)
- 3-May - CDT (RC0), DTP(RC2), EMF (RC2a) , GEF (RC2), VE (M3)
- 5-May - BIRT(RC2), GMF (RC2), TPTP (RC2), WTP (RC2)
- 9-May - admin, mirror propagation
RC3 (23-May)
- 12-May - Platform (RC4)
- 17-May - CDT (RC1), DTP(RC3), EMF (RC4), GEF (RC3), VE (RC1)
- 19-May - BIRT(RC3), GMF (RC3), TPTP (RC2), WTP (RC3)
- 23-May - admin, mirror propagation
RC4 (2 -Jun)
- 26-May - Platform (RC6)
- 29-May - CDT (RC2), DTP(RC4), EMF (RC6a), GEF (RC4), VE (RC2)
- 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
- 2 -June - admin, mirror propagation
RC5 (22-Jun)
- 9-Jun - Platform (M20060609-1217)
- 19-Jun - CDT (RC3) , DTP(RC5), EMF (RC7), GEF (RC5), VE (RCx, none planned)
- 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
- 22-Jun - admin, mirror propagation
RC6 (30-Jun)
- 28-Jun - Platform (Release 3.2)
- 28-Jun - CDT (RC4, if needed) , DTP(RCx, none planned), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
- 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
- 30-Jun - admin, mirror propagation