1. creation of a data model with one requirement type R, one scope S and one traceability link type « R2R » between requirements.
2. creation of a project with 5 requirements R1 to R5 (created with local requirement source)
3. export Recycle configuration and store it in the project.
4. creation of 4 links between those requirements through traceability creator: R1-R2, R1-R3, R1-R4, R1-R5 => can see them immediately in the table.
5. Deletion of first link => it works.
6. Share project to Git (or Perforce) and commit project (all files)
7. Deletion of second link => it works (removed from table)
8. Creation of 2 new links: R2-R3 and R2-R4 => can see them in the table
9. Deletion of last link (R2-R4) => it works
And we can continue with project import by reference:
10. Creation of another workspace WS2
11. Import previous project (import..> existing projects into workspace and select project from git location) - leave « copy in workspace » UNCHECKED to get a reference (not a copy)
12. import Recycle configuration. Can now see requirements and the 3 links in the traceability table.
13. Creation of 1 link R3-R4 (can see it)
14. deletion of R1-R4 => removed
15. Deletion of R3-R4 => removed
We get now 2 links in table: R1-R5 and R2-R3
Now same import of project but with copy.
16.Delete current project from WS2 but do not delete from disk (just from workspace).
17. Import project from git location but check « Copy in workspace »
18. create 2 links R3-R4 and R3-R5
19. deleteR1-R5
20 delete R3-R5 => works