Attendees
- Present:
- Alex Nan
- Rohit Shetty
- Hariharan Narayanan
- Yasuhisa Gotoh
- Absent:
- Richard Yun Song Huang - phone problems
4.4.1
- Monitoring project has executed a final smoke test last week and has successfully finished 4.4.1 testing
4.5
- slow progress has been made on defect fixing, we are behind schedule and at risk of not finishing all targeted defects for 4.5 i6
- Alex
- Rohit
- Gotoh-san
- Hari
- Richard
Action items
- team to focus on reducing defect back log, targetting P1 and high severity defects first
- Alex to open a defect for the Log Analyzer component backward compatibility issue (by the time these notes are written bug 220866 was already opened)
- Hari to contact Alex to decide whether MAX manual tests can be automated using AGR bug 180950
- Gotoh-san to finish ASAP symptom test automation bug 207251
- Richard to get a resolution ASAP on bug 207255