PDE/Plan/4.3
Contents
Overview
This is the PDE project plan for the Eclipse Project Kepler release.
Plan items are listed in the milestone when work is intended to start. Items that take longer than one milestone may be moved after completion. The plan is intentionally heavy on milestones two through five to allow for bug fixing, iterative development, performance and polish work in later milestones.
In Plan - Initial state of planned items, no work currently being done
Investigate - Additional information is being collected
In Progress - Work is being done on the item
Complete - Work is released to a build
Dropped - No longer being worked on for this release
M1 - 10 August 2012
M2 - 21 September 2012
M3 - 2 November 2012
Images View (386197)
M4 - 14 December 2012
Improve Images View (386197)
Improve quickfixes (381975)
M5 - 1 February 2013
Support problem filters on use scans (332772)
Support for declarative services annotations (376950)
M6 - 15 March 2013
(API Freeze)
API tools should work with unresolved bundles (271045)
M7 - 3 May 2013
(Feature Freeze)
Support @noreference on types (235618)
RC Builds - May/June 2013
Unscheduled Items
This section will list items that we are interested in completing during the release, but have not been scheduled. For general ideas, use the Wishlist.