Skip to main content

Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Oxygen/Simultaneous Release Plan


This document is primarily for developers of the June 2017 Oxygen Simultaneous Release.


Requirements For Participation

Projects that are part of Oxygen agree to abide by the requirements of the Eclipse yearly Simultaneous Release.

Milestones and Release Candidates

The Release is always on the fourth Wednesday of June. The milestone dates are at roughly 6-week intervals. Any end-of-cycle release candidate (RC) dates are typically one week apart. Each project has their deliveries due at times offset from the end-date so that the project dependencies can come together in a reasonable order. These delivery times are based on the dependencies between projects. They are labeled +0, +1, +2, and +3, with +0 coming first (the Platform) and "+4" coming last (only EPP packages). Projects themselves decide if they are +0, +1, +2, or +3. The actual time-offset represented by these intervals change over the course of the year of development, being several days at first, but then only one day near the end of the release. The following calendar is the official schedule of the overall Oxygen Release. Projects are free to have their own schedules as long as they meet the Oxygen deliverables.

Note that projects choose their own +n category based on major or primary dependencies. There are many cases where a project might have to deliver pieces of their code a little earlier, if some project depends on it, or a little later if they have a stray dependency. These sorts of deviations are left to the projects to work out, pair-wise, among themselves. Feel free to bring up complicated cases for discussion.

Given all these constraints, the exact dates for any particular year are pretty predictable. The following table summarizes the most significant Oxygen dates but see the subsequent calendar for the important details. That is, your stuff is due earlier than these table dates! Projects need to deliver a week or two before these "end dates", depending on their chosen, committed offset category (+0, +1, etc). Also, to emphasize, the dates represent the last possible date to contribute ... projects are encourage to provide "warm-up" builds a week or two earlier, when possible, as this often helps expose issues that other teams need discussion or that other teams need to react to, before their final delivery.

After RC4 is quiet week. There will be no further builds. That time is reserved for final, in depth testing, and preparation for release. Emergency rebuilds might be considered, by following the usual Planning Council Exception Process, but only for serious, blocking regressions that have a "cross-project" impact.

Note: A rebuild during the quiet, final week before a release implies an automatic slip of one week for the official, simultaneous release date. This applies to all projects that are part of the simultaneous release, since, to name one reason, there is always a chance we'd have to re-spin again, and slip the date a second time. All projects consuming a "re-built" bundle, might also have to rebuild or re-package their deliverables.

Schedule

                                                              Elapsed Weeks
       End Date                       Span from +0         for +0    for EPP avail
M1  Friday, August 12, 2016           08/05 to 08/12          6         6   (from previous release GA)
M2  Friday, September 23              09/16 to 09/23          6         6   (from M1)
  Neon.1 (Wed., 09/28)

M3  Friday, November 04               10/28 to 11/04          6         6   (from M2)
M4  Friday, December 16               12/09 to 12/16          6         6   (from M3) 
  Neon.2 (Wed., 12/21)

M5  Friday, February 03, 2017         01/27 to 02/03          7         7   (from M4) (extra week for end-of-year holidays)
M6  Friday, March 17                  03/10 to 03/17          6         6   (from M5)   
  Neon.3 (Thursday, 03/23) *In practice will be ready before the conferences start.
  Devoxx US (03/21 to 03/23)
 
M7  Friday, May 19                    05/12 to 05/19          7         7   (from M6) (extra week for EclipseCon)

RC1 Friday, May 26                    05/19 to 05/26          1         1   (from M7)
RC2 Friday, June 02                   05/26 to 06/02          1         1   (from RC1)
RC3 Friday, June 09                   06/02 to 06/09          1         1   (from RC2)
RC4 Friday, June 16                   06/09 to 06/16          1         1   (from RC3)

Quiet week, June 19 to June 27
 No builds during "quiet week". It is assumed all code is done by the end of RC4.
 
Release Wednesday, June 28, 2017



The calendar is available in the following formats: ICal,HTML

Communication Channels

Cross-Project Milestone & RC Status Reporting

Only negative status needs to be reported. It is essential for many aspect of the simultaneous release that communication be prompt and clear, on many topics. One of the most important ones, is if someone is not meeting some date or delivery. Put another way, we assume everyone is on target and has delivered their stuff unless a note is sent to cross-project list that you are delayed. Its better to be up front about it, so everyone knows what to expect, rather than to hope things turn out ok at the very last minute, since if you "miss" without saying anything you are more likely to impact other people, and miss your chance to be part of the release.

Mailing Lists and Newsgroups

Eclipse projects have three communication channels: a mailing list for developers, a newsgroup for users, and Bugzilla. While Oxygen is not a "project" per se, it will use the same structure:

Developer mailing list
  • cross-projects-issues-dev - mailing list for developers and releng (see archives). This is the list to use to discuss build issues, announce changes in plans, slippage in deliverables, etc.
Users news group
Bugzilla

If there is any doubt about where a bug belongs, it can always start in the "Cross-Project" component. (Under Eclipse Foundation > Community). If it turns out to be a single project's responsibility, it can be moved to that project. If it is a true cross-project bug, where several projects need to act, then it can stay in the cross-project component.

The Planning Council Mailing List

Because there has been confusion in the past, we'll be explicit here that the planning council mailing list (eclipse.org-planning-council) is for Planning Council business, not the Oxygen Release activities per se. While they sometimes overlap, there is no need to cross post. While anyone can request a subscription to the planning council list (for openness and transparency) the expectation is that only Planning Council members post to it.

Conference Calls

The Planning Council has regularly scheduled calls for Planning Council business. See conference calls.

But there are no planned calls for the release, per se, or for larger audiences, but they can be arranged if required or desired (for example, if needed for build coordination).

Builds and P2 repository

Builds (Aggregation)

This section, about assembling the repositories, is subject to change, as improvements in the process are made.

A number of utilities have been written to automate the assembly of Callisto '06, Europa '07, Ganymede '08, Galileo '09, Helios '10, Indigo '11, Juno '12, Kepler '13, Luna '14, Mars '15, and now Oxygen '16 builds. These are available in their own SCM repository. If interested in this history, you can find more information about the history and organization by looking at some of the old, previous information on the Contributing to Helios Build, Galileo Build, Ganymede Build and Europa Build pages).

With Oxygen (and Neon.2) we are using the CBI Aggregator (effective 11/2016 we switched from "b3" aggregator to "CBI aggregator").

The Contributing to Simultaneous Build page is where you go to learn how to add your project to the Oxygen build (aggregation).

p2 Repository

To obtain the latest published bits from Oxygen, use this URL:

http://download.eclipse.org/releases/oxygen

It contains the latest milestone, release candidate, eventually the release itself, and then eventually the update releases.

To obtain the latest working version, as we build up to a milestone or release, you can test the site at

http://download.eclipse.org/staging/oxygen

Update Releases

There will be 3 update releases for Oxygen, similar to Neon's Update Releases. These will be roughly equally spaced so there is one per quarter. These update releases will be done in parallel with every other milestone of the Photon release; so milestones 2, 4 and 6.

Interlock of Milestones and Update releases

The following table illustrates the pattern the milestones and update releases will release at the same time.

Stream/Week 0 1 2 3 4 5 6 release day 0 1 2 3 4 5 6 release day
master dev dev dev dev dev stabilize/+0 +1 to release Odd Milestone (1,3,5,7) dev dev dev dev dev stabilize/+0 +1 to release Even Milestone (2,4,6)
udpates dev dev dev dev dev dev dev dev dev dev RC1 RC2 RC3 RC4 Quiet Week Update.n (1,2,3)

The weeks are numbered in the table above 0 to 6 because ideally there are 6 weeks per milestone, but sometimes there are 7, and occasionally 8 and I think once 5!. It was thought best to have the table end with "6" to represent the ideal.


Staging repositories

We will have named staging repositories for each stream as we work on Update Releases:

http://download.eclipse.org/staging/oxygen

Schedules

Oxygen.1

GA: 9/27/2017 (fourth Wednesday of September)

In the Oxygen.1 ramp down, as shown in the following table, there will be 4 RCs, each one of those spanning just one week, with projects staging themselves into the build just one day apart.

Projects may elect not to participate in any particular RC (and just contribute what's already there), but projects do have an obligation to fix any build problems that are related to their code or p2 repositories during each RC if any such problems arise.

RC1 is really a "warm-up" RC, just to make sure we can still build, etc. Subsequent RCs are expected to be true "Release Candidates", suitable for acceptance testing, etc.

The Final week before GA will not have any further builds or contributions, but instead be reserved for final adopter testing and site preparations. Only emergency fixes for very serious regressions that effect many projects or the general ability to install or update will be considered as a reason to rebuild during the final quiet week.

The 'promote period' (9/23 to 9/26) will be the time projects put final zips and repository artifacts in their final release location (but, without displaying them or making them visible to p2) so they can propagate through the mirroring system (but not generally be "visible" to end users or p2, so that there really is a "simultaneous maintenance release"). At 9 AM (Eastern), on the GA date, projects can make their final maintenance releases visible. (Be sure to check cross-project list, first, to make sure there's not any last-minute blocking problems or changes to exact times).

Note: the due time is 5 PM (Eastern) and availability time is 9 AM (Eastern) unless otherwise communicated on cross-project list.

+0
Fri.
+1
Mon.
+2
Tues.
+3
Wed.
EPP
Thur.
Available
Fri.
RC1 (Warmup) 8/18 8/21 8/22 8/23 8/24 8/25
RC2 8/25 8/28 8/29 8/30 8/31 9/01
RC3 9/01 9/04 9/05 9/06 9/07 9/08
RC4 9/08 9/11 9/12 9/13 9/14 9/15
Quiet week quiet: 9/15 quiet: 9/18 quiet: 9/19 quiet: 9/20 quiet: 9/21 quiet: 9/22
Oxygen.1 ("GA") quiet: 9/22 quiet: 9/25 quiet: 9/26 GA: 9/27

Oxygen.1a

GA: 10/11/2017 (second Wednesday of October)

Only projects providing changes needed for Java 9 or JUnit 5 can participate in this release.

+0
Fri.
+1
Mon.
+2
Tues.
+3
Wed.
EPP
Thur.
Available
Fri.
RC1 09/22 09/25 09/26 09/27 09/28 09/29
RC2 09/29 10/02 10/03 10/04 10/05 10/06
Oxygen.1a ("GA") quiet: 10/06 quiet: 10/09 quiet: 10/10 GA: 10/11

Oxygen.2

GA: 12/20/2017 (third Wednesday of December)

Rampdown principles similar to Oxygen.1.

+0
Fri.
+1
Mon.
+2
Tues.
+3
Wed.
EPP
Thur.
Available
Fri.
RC1 (Warmup) 11/10 11/13 11/14 11/15 11/16 11/17
RC2 11/17 11/20 11/21 11/22 11/23 11/24
RC3 11/24 11/27 11/28 11/29 11/30 12/1
RC4 12/1 12/4 12/5 12/6 12/7 12/8
Quiet week quiet: 12/8 quiet: 12/11 quiet: 12/12 quiet: 12/13 quiet: 12/14 quiet: 12/15
Oxygen.2 ("GA") quiet: 12/15 quiet: 12/18 quiet: 12/19 GA: 12/20

Oxygen.3

GA: 3/21/2018 (third Wednesday of March)

Rampdown principles similar to Oxygen.1.


+0
Fri.
+1
Mon.
+2
Tues.
+3
Wed.
EPP
Thur.
Available
Fri.
RC1 (Warmup) 2/9 2/12 2/13 2/14 2/15 2/16
RC2 2/16 2/19 2/20 2/21 2/22 2/23
RC3 2/23 2/26 2/27 2/28 3/01 3/02
RC4 3/02 3/05 3/06 3/07 3/08 3/09
Quiet week quiet: 3/09 quiet: 3/12 quiet: 3/13 quiet: 3/14 quiet: 3/15 quiet: 3/16
Oxygen.3 ("GA") quiet: 3/16 quiet: 3/19 quiet: 3/20 GA: 3/21

Oxygen.3a

GA: 04/11/2018 (second Wednesday of April)

Only projects providing changes needed for Java 10 (18.3) can participate in this release.

+0
Fri.
+1
Mon.
+2
Tues.
+3
Wed.
EPP
Thur.
Available
Fri.
RC1 03/23 03/26 03/27 03/28 03/29 03/30
RC2 03/30 04/02 04/03 04/04 04/05 04/06
Oxygen.3a ("GA") quiet: 04/06 quiet: 04/09 quiet: 04/10 GA: 04/11

Other considerations and rules

Individual projects may have their own update releases at any time if they need to, but all participants in the Simultaneous Release, are expected to participate fully in the Simultaneous Updates. What new features are added or what bugs are fixed is up to each project to decide, but each project must, at least, continue to "fit in"; build, install and avoid conflicts. To be explicit, new projects may join Update Releases, and participating projects may add new features or APIs (i.e. contribute Minor Releases) if they would like to. It is expected that many projects will primarily provide service-only updates, but it is up to each project to decide. The main rule is that no one can add breaking changes. This means no API breakages, and features can not be removed (for technical reasons) or refactored in a way that breaks others that "include" the feature;. If the contents of feature's change, due to refactoring, for example, it is best to do in a way that does not break existing adapters or projects that build against, or "include" that feature. Note: even breaking changes can be made, but those are the exception, rather than the rule, and must go through the Planning Council's formal Exception Process. Another important rule is that new projects and even new features must be essentially complete, including release review records, by RC1. Anything later than that must also go through the Planning Council's formal Exception Process.

Back to the top