Agenda Jan 14 2009

Attendees:

Peter K.

Guy

Mike N.

Eric

Tom

Neil

Michael O.

David T.

Blaise

Shaun

Doug

Mitesh



  • IP review process is backlogged, will send out for review later today.
    • Feb 4th release may be at risk but not much.
    • Moved code freeze to next week
  • Project status
    • Handing in ip log today
  • Action: Verify 3rd party checkins are included with automatically generated ip
  • Derived IDs, reviewed
  • Mapped by ID have some open issues
  • Extended maps in queue
  • Annotations for collections in queue
  • DBWS
    • Reduced use cases for proof of concept for pl/sql support
    • Need to transition to production code
    • Need to decide what is going in for code freeze - describe for user " I have added X to do Y"
  • SDO 2.1.1 and 2.1.0
    • Closing down final bugs
    • JSR 235 is still in public review - therefore the 2.1.1 API may change
    • Resolved what will be done for the SDO CQ - we will go with 2.1.0
    • M6 was built with the 2.1.1 version before 2.1.0 rollback
  • Bugs
    • The 1.1 P2 bugs are all assigned and on track
  • Mitesh? Is anyone viewing the TCK pages?
    • A) yes, chris is looking at it


  • No new general issues

Back to the top