Category:SimRel-2020-09
This documents related to 2020-09, the Eclipse Foundation's multi-project Simultaneous Release of September 2020.
Simultaneous Release | ||
Preceded by SimRel-2020-06 |
2020-09 2020 |
Succeeded by SimRel-2020-12 |
Common information
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release schedule
Release | Date | Span | Due dates | Notes |
---|---|---|---|---|
2020-09 M1 | Friday, July 17, 2020 | 07/10 to 07/17 |
|
3 weeks from 2020-06 GA |
2020-09 M2 | Friday, August 7, 2020 | 07/31 to 08/07 | 3 weeks from M1 | |
2020-09 M3 | Friday, August 28, 2020 | 08/21 to 08/28 |
|
3 weeks from M2 |
2020-09 RC1 | Friday, September 4, 2020 | 08/28 to 09/04 |
|
1 week from M3 |
2020-09 RC2 | Friday, September 11, 2020 | 09/04 to 09/11 | 1 week from RC1 | |
Quiet period | 09/11 to 09/15 | No builds during "quiet period". It is assumed all code is done by the end of RC2. | ||
2020-09 GA | Wednesday, September 16 2020 |
|
5 days from RC2 |