Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "PTP/meetings/September 2008"
(New page: == September 2008 Meeting == Date: September 9, 2008 Time: 1:00 PM EST Call in information: Toll Free (US): 1 877-421-0033<br> Toll Free (Germany): 0800-181-6323<br> Local (US): +1 770-...) |
(→Agenda) |
||
Line 22: | Line 22: | ||
#* UNICORE integration | #* UNICORE integration | ||
# Next meeting | # Next meeting | ||
+ | |||
+ | == Attendees == | ||
+ | * Greg Watson, IBM Research | ||
+ | * Beth Tibbitts, IBM Research | ||
+ | * Dave Wootten, IBM | ||
+ | * Chris Recoskie, IBM | ||
+ | * Mike Kucera, IBM | ||
+ | * Daniel Ferber, IBM | ||
+ | * Max Billingsley, U. Florida | ||
+ | * Wyatt Spear, U. Oregon | ||
+ | * Shebhaz, Juelich Supercomputing Center | ||
+ | |||
+ | == Minutes == | ||
+ | |||
+ | PTP 2.1 | ||
+ | * M1 build is now available. Problems with creating build still being addressed. M1a probably available shortly. M1 does not contain Performance Tools Framework (PTFw) yet. | ||
+ | * Chris and Vivian are working on pacakaging RDT remote jars including eclipse platform jars required for remote RDT server. | ||
+ | |||
+ | Project Reports | ||
+ | * PLDT (Beth) - looking at bugzilla to fix some bugs before 2.1 release. TaskFinder, using PTFw, probably will not be in PTP 2.1 release after all. | ||
+ | * Debugger (Greg) - Greg is working with Dave W on making PE work with PTP debugger | ||
+ | * RDT (Chris) - working on bugs and build; new Remote C/C++ Perspective coming. | ||
+ | ** New Remote Project wizard - flow isn't ideal, but is using Eclipse platform wizard infrastructure. More things handled correctly by default now (e.g. Connection) - still need more | ||
+ | * Performance Tools Framework (Wyatt) - working on parametric improvements to e.g. handle ranges of arguments and environment variables and then run trials in sequence (scenarios) and manage the results. | ||
+ | ** Still has not tested PTFw on remote projects via RDT. Not sure this will happen before 2.1. | ||
+ | ** Working on performance data management | ||
+ | * Unicore ( Shebhaz) - Job submission and management, Unicore is used extensively in Europe. See http://unicore.eu for more information. | ||
+ | ** Middleware which allows control of backend systems e.g. OpenPBS, LoadLeveler, etc. | ||
+ | ** Frontend clients can be eclipse, command line, Java/Swing | ||
+ | ** Intend to start work in November | ||
+ | * Parallel Performance Wizard (Max) - Perf. tools for PGAS systems esp. UPC and SHMEM. | ||
+ | ** PPW will be integrated with PTP via PTFw initially. Has an initial tool.xml | ||
+ | ** Max tried using UPC with CDT, has some questions and will ask on CDT mailing list or newsgroup. Need "New UPC Project" wizard. | ||
+ | ** UPC developer's working that Max will attend in approx. 2 weeks - hopes to start discussion of tools there. | ||
+ | * Remote Tools (Daniel) - changes to the way Remote Tools displays connection information | ||
+ | |||
+ | Next meeting October 14 |
Revision as of 17:05, 9 September 2008
September 2008 Meeting
Date: September 9, 2008 Time: 1:00 PM EST
Call in information:
Toll Free (US): 1 877-421-0033
Toll Free (Germany): 0800-181-6323
Local (US): +1 770-615-1250
Local (Germany): +49 695-170-9081
Passcode: 583191
Agenda
- PTP Status
- 2.1 release update
- Project Reports
- Debugger
- PLDT
- RDT
- UNICORE integration
- Next meeting
Attendees
- Greg Watson, IBM Research
- Beth Tibbitts, IBM Research
- Dave Wootten, IBM
- Chris Recoskie, IBM
- Mike Kucera, IBM
- Daniel Ferber, IBM
- Max Billingsley, U. Florida
- Wyatt Spear, U. Oregon
- Shebhaz, Juelich Supercomputing Center
Minutes
PTP 2.1
- M1 build is now available. Problems with creating build still being addressed. M1a probably available shortly. M1 does not contain Performance Tools Framework (PTFw) yet.
- Chris and Vivian are working on pacakaging RDT remote jars including eclipse platform jars required for remote RDT server.
Project Reports
- PLDT (Beth) - looking at bugzilla to fix some bugs before 2.1 release. TaskFinder, using PTFw, probably will not be in PTP 2.1 release after all.
- Debugger (Greg) - Greg is working with Dave W on making PE work with PTP debugger
- RDT (Chris) - working on bugs and build; new Remote C/C++ Perspective coming.
- New Remote Project wizard - flow isn't ideal, but is using Eclipse platform wizard infrastructure. More things handled correctly by default now (e.g. Connection) - still need more
- Performance Tools Framework (Wyatt) - working on parametric improvements to e.g. handle ranges of arguments and environment variables and then run trials in sequence (scenarios) and manage the results.
- Still has not tested PTFw on remote projects via RDT. Not sure this will happen before 2.1.
- Working on performance data management
- Unicore ( Shebhaz) - Job submission and management, Unicore is used extensively in Europe. See http://unicore.eu for more information.
- Middleware which allows control of backend systems e.g. OpenPBS, LoadLeveler, etc.
- Frontend clients can be eclipse, command line, Java/Swing
- Intend to start work in November
- Parallel Performance Wizard (Max) - Perf. tools for PGAS systems esp. UPC and SHMEM.
- PPW will be integrated with PTP via PTFw initially. Has an initial tool.xml
- Max tried using UPC with CDT, has some questions and will ask on CDT mailing list or newsgroup. Need "New UPC Project" wizard.
- UPC developer's working that Max will attend in approx. 2 weeks - hopes to start discussion of tools there.
- Remote Tools (Daniel) - changes to the way Remote Tools displays connection information
Next meeting October 14