Difference between revisions of "XSL Release Plan"
(Added 0.5M9 plan items) |
|||
Line 16: | Line 16: | ||
Please Review the [https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=allwordssubstr&short_desc=%5Bxslt%5D&classification=WebTools&product=Web+Tools&component=incubator&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug_status=NEW&bug_status=ASSIGNED&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&field0-0-0=noop&type0-0-0=noop&value0-0-0= current backlog] and add a target milestone of 0.5M8 to any items you plan to work on during the iteration. | Please Review the [https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=allwordssubstr&short_desc=%5Bxslt%5D&classification=WebTools&product=Web+Tools&component=incubator&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug_status=NEW&bug_status=ASSIGNED&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&field0-0-0=noop&type0-0-0=noop&value0-0-0= current backlog] and add a target milestone of 0.5M8 to any items you plan to work on during the iteration. | ||
+ | |||
+ | |||
+ | ==0.5M9== | ||
+ | |||
+ | '''Goals:''' Project Specific Validation, Bug Cleanup, and Stabilization | ||
+ | |||
+ | '''Testing Week: August 4, 2008''' | ||
+ | |||
+ | '''0.5M9 Build Declared: August 11, 2008''' | ||
+ | |||
+ | |||
+ | The current [https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=allwordssubstr&short_desc=&classification=WebTools&product=Web+Tools&component=incubator&target_milestone=0.5+M9&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&field0-0-0=noop&type0-0-0=noop&value0-0-0= iteration plan]. Any bug you target as being in 0.5M9 will show up in the plan list. | ||
==0.5M8== | ==0.5M8== |
Revision as of 18:53, 7 July 2008
The following is a tentative schedule of dates for the XSL Tooling Project. An official release date has not been set, and the best answer at this time is "when it's ready." With that said, the XSL Tool Project will be following closely the WTP Release schedule, but will not be included in the Ganymede release.
About Version Numbering
Since the XSL Tooling project is based off of initial code contributions from both the X-Assist and OrangeVolt.com Eclipse XSLT editors. It was decided that that initial version would start off at 0.5. The first M build will start with M4 to better signify what version of WST should be used.
Schedule
The first public build version is scheduled for January 21, 2008, and will be 0.5M4. To this affect the XSL Tooling project will aim to follow the build schedule of WTP.
The calendar is available in the following formats: ICal,ATOM News Feed,HTML
Please only select items that you feel you can complete. If there is a feature listed in the requirements page, that doesn't have a bug please create one for it as well. Anything that is planned to be worked on should have a bug entered to track it's progress.
Please Review the current backlog and add a target milestone of 0.5M8 to any items you plan to work on during the iteration.
0.5M9
Goals: Project Specific Validation, Bug Cleanup, and Stabilization
Testing Week: August 4, 2008
0.5M9 Build Declared: August 11, 2008
The current iteration plan. Any bug you target as being in 0.5M9 will show up in the plan list.
0.5M8
Goals: XPath Content Assistance improvement, Project Specific Validation Preferences
Testing Week: June 16, 2008
0.5M8 Build Declared: June 23, 2008
The current iteration plan. Any bug you target as being in 0.5M8 will show up in the plan list.
0.5M7
Goals: Validation and Bug Fixes.
Testing Week: April 28, 2008
0.5M7 Build Declared: May 7, 2008
The current iteration plan. Any bug you target as being in 0.5M7 will show up in the plan list.
0.5M6
Goals: XInclude, Docbook, and XSL Content Assistance.
Testing Week: March 31, 2008
0.5M6 Build Declared: April 7, 2008
The current iteration plan. Any bug you target as being in 0.5M6 will show up in the plan list.
0.5M5
Testing Week: February 10, 2008
0.5M5 Build Declared: February 17, 2008
Please Review the current backlog and add a target milestone of 0.5M5 to any items you plan to work on during the next month.
The current iteration plan. Any bug you target as being in 0.5M5 will show up in the plan list.
Please only select items that you feel you can complete. If there is a feature listed in the requirements page, that doesn't have a bug please create one for it as well. Anything that is planned to be worked on should have a bug entered to track it's progress.