Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

WTP 2010-07-01

Revision as of 23:16, 30 June 2010 by David williams.acm.org (Talk | contribs) (7/1)

WTP Development Status Meeting

Attendees

Project Leads
Carl
Tim
Keith
Nitin
Chuck
Kaloyan
Raghu
Neil
David
Committers
Bob
Konstantin
Chris
Dave
Larry
Kate
Angel
Valentin
Paul
Nick
Gabriel
Eric
Rob
Sam
Friends
Elson
Ian
Aidyl

Note: feel free to correct any errors/omissions in above attendance record.

Remember, any committer can add an agenda item. Typically, short announcements or news items go in the "Announcements" section at the beginning. Longer items or issues requiring discussion should go in the "Other business" section at end.

Announcements And Special Reports

WTP Calendar

(Weekly Google Calendar updated through June, 2010)


For Helios overall dates, see a Simultaneous Release Calendar


WTP 3.2.1


  • Bug Review
Hotbugs [1]
Blocker and Critical
P1s that need attention

Schedule

6/16 Map files branched, M (continuous) builds started
Project lead review and approval until July 1
7/1 Declared M-build RC1
PMC +1 review: July 2 - July 8
7/8 Declared M-build RC2
PMC +2 review: July 9 - July 15
7/15 Declared M-build RC3 <== final build, unless blockers found
PMC +3 review: July 16 - July 22
7/22 Declared M-build RC4 <== final build, if needed
July 23 - July 30 is "quiet week" to allow in depth testing with no changes
7/30 Official Release

See "references" [2] for detailed explanation of what these dates mean.

WTP 3.3.0

Initial Planning during July? Final plans by end of September?

Working assumption: objective is to work with both Platform 3.7 and 4.0?

Other business

  •  ?

References

  1. Hotbug Policy
  2. Our plan dates are on 'Friday' of the week. But, we produce and test the build on Thursday of the week, and ideally declare on Thursday. The dates in the Google Web Tools group calendar are for 'Thursdays' since that's a calendar for committers. We give ourselves the buffer to Friday, as our "public" date, that others can pick up our build, just in case a regression is found on Thursday and we have to respin and retest. [Technically, some might say, we still have till the following Tuesday or Wednesday for some "Simultaneous Release" due dates ... but it's hard to do much in that window, without disrupting everyone ... so we'll not use that buffer, except for the worst emergencies.]

Also, see

WTP 3.2.x maintenance release plan

how/when to branch code?

WTP_3.2_Ramp_down_Plan_for_Helios

Web Tools Platform Plans

IP Logs selector

WTP Helios retrospective.


See also the WTP Meeting Archive-Reference Page.

Back to the top