− | = <i>Finding That WTP Build Rhythm</i> = | + | = <i>Finding That Sweet WTP Build Rhythm</i> = |
Line 26: | Line 26: | ||
*Team development continues. | *Team development continues. | ||
+ | |||
+ | |||
+ | ;[[WTP Build Process and Procedures | Back to WTP Build Process and Procedures]] | ||
+ | ;[[Web_Tools_Project | Back to Web Tools Wiki Home]] |
Revision as of 16:49, 17 January 2007
Contents
Finding That Sweet WTP Build Rhythm
Monday
- Team development.
Tuesday
- Team development.
- Prerequisite dependencies finalized and in the builds.
Wednesday
- Team development
- Weekly candidate build produced (roughly midnight EST) and smoke test wiki page created.
- -Once this build is created, teams should not commit any more changes until the build is declared.
Thursday
- Team's smoke test and report status on wiki page by 2 PM EST.
- If a team needs to respin for a severe issue, the team may do so provided they report a failed smoke test status on the wiki and send a note to wtp-releng@eclipse.org with the defect number and explanation of which teams will need to re-smoke test the new build.
- Discuss declaration of the weekly build during the WTP Status Call.
Friday
- Team development continues.