Talk:Planning Council/June 08 2016

Some hypothetical dates for Neon.1 - 3 and Oxygen.0.M1 - M6:

Oxygen.0.M1

  • 2016/08/05-18 Oxygen.0.M1 +0 through EPP
  • 2016/08/19 Oxygen.0.M1 declared

Conferences & Events

Oxygen.0.M2 / Neon.1

Neon.1

  • 2016/08/01 Deadline for projects to declare intent and be part of the Neon.1 and Oxygen.0.M2 builds

  • 2016/08/19-25 Neon.1.RC1 +0 through EPP
  • 2016/08/26 Neon.1.RC1 declared

  • 2016/08/26-01 Neon.1.RC2 +0 through EPP
  • 2016/09/02 Neon.1.RC2 declared

  • 2016/09/02-08 Neon.1.RC3 +0 through EPP
  • 2016/09/09 Neon.1.RC3 declared

  • 2016/09/09-15 Neon.1.RC4 +0 through EPP
  • 2016/09/16 Neon.1.RC4 declared

  • 2016/09/19-22 Quiet Week
  • 2016/09/23 Neon.1 declared

and, in parallel

Oxygen.0.M2

  • 2016/09/09-22 Oxygen.0.M2 +0 through EPP
  • 2016/09/23 Oxygen.0.M2 declared

Conferences & Events

Oxygen.0.M3

  • 2016/10/28-10 Oxygen.0.M3 +0 through EPP
  • 2016/11/11 Oxygen.0.M3 declared

Conferences & Events

Oxygen.0.M4 / Neon.2

Neon.2

  • 2016/11/01 Deadline for projects to declare intent and be part of the Neon.2 and Oxygen.0.M4 builds

  • 2016/11/21-24 Neon.2.RC1 +0 through EPP
  • 2016/11/25 Neon.2.RC1 declared

  • 2016/11/25-01 Neon.2.RC2 +0 through EPP
  • 2016/12/02 Neon.2.RC2 declared

  • 2016/12/02-08 Neon.2.RC3 +0 through EPP
  • 2016/12/09 Neon.2.RC3 declared

  • 2016/12/09-15 Neon.2.RC4 +0 through EPP
  • 2016/12/16 Neon.2.RC4 declared

  • 2016/12/19-22 Quiet Week
  • 2016/12/23 Neon.2 declared

and, in parallel

Oxygen.0.M4

  • 2016/12/16-22 Oxygen.0.M4 +0 through EPP
  • 2016/12/23 Oxygen.0.M4 declared

Conferences & Events

Oxygen.0.M5

  • 2017/01/27-02 Oxygen.0.M5 +0 through EPP
  • 2017/02/03 Oxygen.0.M5 declared

Conferences & Events

Oxygen.0.M6 / Neon.3

Neon.3

  • 2017/02/01 Deadline for projects to declare intent and be part of the Neon.3 build (too late to join Oxygen)

  • 2017/02/10-16 Neon.3.RC1 +0 through EPP
  • 2017/02/17 Neon.3.RC1 declared

  • 2017/02/17-23 Neon.3.RC2 +0 through EPP
  • 2017/02/24 Neon.3.RC2 declared

  • 2017/02/24-02 Neon.3.RC3 +0 through EPP
  • 2017/03/03 Neon.3.RC3 declared

  • 2017/03/03-09 Neon.3.RC4 +0 through EPP
  • 2017/03/10 Neon.3.RC4 declared

  • 2017/03/13-16 Quiet Week
  • 2017/03/17 Neon.3 declared

and, in parallel

Oxygen.0.M6

  • 2017/03/10-16 Oxygen.0.M6 +0 through EPP
  • 2017/03/17 Oxygen.0.M6 declared