Attendees
- Present:
- Alex Nan
- Yasuhisa Gotoh
- Richard Yun Song Huang
- Rohit Shetty
- Absent:
- Hariharan Narayanan - on vacation
4.4.1
4.5
- 4.5 i3 TP1 finished
- still an outstanding test suite to run Monitor.UI.Common.Services
- some of the BTM test results were not checked into CVS yet
- iteration numbers have shifted out by 2 to align with the Eclipse Ganymede milestone numbers
- Alex has updated i2 and i3 targetted defects to i4 and i5
- work in progress on 207240
- work in progress on 208586
- in TP2 we will run only a smoke test since no defects were fixed in TP1
- in the remaining spare time to try finishing the test case automation work
- new defects have been opened by Marius to track the work for the features 200138, 200139
- new defects have been opened, reported by a consuming product:
- 207763
- 207806
- could be potential 4.4.1 candidates
- consuming product will likely request a patch on TPTP4.2.2
- after TP2 the focus should be on reducing the backlog of defects and feature work
Action items
- Richard to check in the remaining BTM test results
- Rohit to fix 206260 as soon as possible
- Alex to finish 206665 as soon as possible
- Alex in collaboration with Joel and Samson to finish 208586
- Alex to define the smoke test content (at the time these notes are written this is already done)
- Alex (with Marius) to finish work on 207240
- finish TP2 by Friday November 9, 2007 (worse case by Tuesday November 13, 2007)