Line 17: Line 17:
 
** Multiple servers bridged together
 
** Multiple servers bridged together
 
* Goal of the testing will be to create a report showing the successful interoperability between different products.
 
* Goal of the testing will be to create a report showing the successful interoperability between different products.
 +
 +
3. Schedule
 +
 +
* Dec. 1: start promoting the event and recruiting participants. Ensure we have the wiki page up to date and in a state that it will communicate the goals, objectives and reason to participate. Ian S. will be responsible for recruitment and promotion
 +
* mid-Jan or before: draft test cases made available. Ian C will be responsible for test cases.
 +
* Feb 1: First phone call with participants to discuss preparation requirements to be completed before the testing day.
 +
* March 17: Testing day at EclipseCon

Latest revision as of 13:17, 10 December 2013

Meeting Minutes - Nov 4, 2013

1. Review logistics

  • Assumption is maximum 20 different 'products' will participate, minimum 10. Suggest to limit 2 attendees per product.
  • Ian S will secure a room at EclipseCon for Monday, March 17. Room will be setup to have 10 different work areas to support pair-wise testing.
  • Internet access is always a challenge so we need to make sure we can do testing without direct access.
  • Participation will be free for conference attendees. However non-EclipseCon attendees might have to pay a fee to cover the F&B cost.


2. Suggested agenda items

  • Update on standard efforts by TC chairs
  • Most of the day will be a series of testing sessions between the participants. Types of testing will include the following:
    • Pair-wise testing between a client product and a server product
    • Multiple different clients testing against a server
    • Multiple servers bridged together
  • Goal of the testing will be to create a report showing the successful interoperability between different products.

3. Schedule

  • Dec. 1: start promoting the event and recruiting participants. Ensure we have the wiki page up to date and in a state that it will communicate the goals, objectives and reason to participate. Ian S. will be responsible for recruitment and promotion
  • mid-Jan or before: draft test cases made available. Ian C will be responsible for test cases.
  • Feb 1: First phone call with participants to discuss preparation requirements to be completed before the testing day.
  • March 17: Testing day at EclipseCon