=Final Release Day=
 
=Final Release Day=
In the final release day, as it's specified by the [[Kepler/Simultaneous_Release_Plan#Milestones_and_Release_Candidates | Simulatenous Release Planning]] (''Kepler'' by the time of writing), we need to activate our final release to be downloaded from our public downloads area and from our public ''updates/releases'' p2 repository. To accomplish that, the following tasks need to be undertaken.
+
The R-build is automatically published, so no immediate action is required.
 
+
==Show the new release in the downloads web page==
+
Basically, we have to follow similar steps to those we did to hide the release. Providing you have previously imported the '''mdt''' project from the cloned GIT repository, the steps to do are the following:
+
*Edit the '''/mdt/downloads/hidden.txt''' file and remove the entry for the new release to make it visible.
+
*Commit and push the change to the remote repository
+
 
+
==Make the new release p2 repository available==
+
During the ''quiet week'', we prepared the p2 repository under the ''updates/releases'' folder. However the new release repository needs to be published by including it in our public ''updates/releases'' (composite) ''updates/releases/latest'' (composite) repositories. To do that we will simply have to use the [[Modeling_Project_Builds/Utilities#manage-composite.xml | Manage Composite Utility]] to add the new release (twice) and remove the previous latest release (once). For instance for the Juno SR2 release:
+
 
+
cd ~/downloads/modeling/mdt/ocl/updates/releases
+
~/downloads/modeling/mdt/ocl/updates/releases> ant -f /shared/modeling/tools/promotion/manage-composite.xml add -Dchild.repository=4.0.2
+
cd latest
+
~/downloads/modeling/mdt/ocl/updates/releases> ant -f /shared/modeling/tools/promotion/manage-composite.xml add -Dchild.repository=../4.0.2
+
~/downloads/modeling/mdt/ocl/updates/releases> ant -f /shared/modeling/tools/promotion/manage-composite.xml remove -Dchild.repository=../4.0.1
+
  
 
==Update Eclipse Market Entry==
 
==Update Eclipse Market Entry==
Line 77: Line 63:
  
 
[http://marketplace.eclipse.org/content/eclipse-ocl#.UT2sXhzJT2s Eclipse OCL at Market Place]
 
[http://marketplace.eclipse.org/content/eclipse-ocl#.UT2sXhzJT2s Eclipse OCL at Market Place]
 +
 +
==Next Version==
 +
The Eclipse OCL entry in the Eclipse MarketPlace requires to be updated with the final R-build:
 +
The project should be moved onto the next release number by editing the many version numbers in MANIFEST.MF, pom.xml, feature.xml. Once this has been debugged using a local Tycho build, the Promoter job can be re-enabled.
  
 
==Announcement==
 
==Announcement==
 
Remember to announce the new release in our public [http://www.eclipse.org/forums/index.php?t=thread&frm_id=26 forum].
 
Remember to announce the new release in our public [http://www.eclipse.org/forums/index.php?t=thread&frm_id=26 forum].

Revision as of 06:54, 10 September 2019

In this wiki entry we explain the releng bits that may be done during the quiet week, particularly to the Eclipse OCL project. You may find some general information about the quite week in the Simultaneous Release Final Daze documentation (Juno, for the time of writing).

The main purpose of the quite week activities is preparing the downloadable zips and the release p2 repository in its final location so that they are properly mirrored across the different mirror servers prior to the final release date, taking into account that the content can't be available for download until that date. The releng tasks to be done are explained in two blocks, the tasks during the Quite Week and those tasks which must be done the Final Release Day.

Quiet Week

The following are the Eclipse OCL usual releng tasks to be accomplished during the quiet week.

Hide the new release in the downloads web page

Prior to prepare the downloadable zips of the imminent release in the downloads area, we should ensure that it's not available for downloading. To do that you must follow the following steps:

   note: see the hidden.txt file history to find examples of previous modifications
  • Commit and push the change to the remote repository

Prepare the downloadable zips area

The former practice contributed the final RC-build to SimRel and performed a number of manual rename activities once the build was successful and ready to be published. These manual activities are hard now that the remote access to build.eclipse.org is more restricted.

There is now no need to prepare a downloads area. Just perform an R-build with an alias of the release name. Do this as late as practical before the final SimREl build so that the R-build can be contributed to the SimRel aggregator.

Archive old releases

Older download ZIPs are moved to archive:

  • Edit the /mdt/downloads/extras-ocl.php file to add the redirections for archived releases
  • Copy the releases to archive
cd ~/downloads/modeling/mdt/ocl/downloads/drops
mv 5.0.5 /home/data/httpd/archive.eclipse.org/modeling/mdt/ocl/downloads/drops

*Make sure the archive is useable For each new archived R folder that doesn't have an index.php

cp ../../3.1.0/R201106061427/index.php .

The default Eclipse Foundation archive.eclipse.org 404 page has a "Show Directory Contents." that provides similar/better functionality than the traditional project index.php.

Older P2 repos are moved to archive:

  • Copy the repo to archive
cd ~/downloads/modeling/mdt/ocl/updates/releases
ant -f /shared/modeling/tools/promotion/manage-composite.xml remove -Dchild.repository=5.0.5
mv 5.0.5 /home/data/httpd/archive.eclipse.org/modeling/mdt/ocl/updates/releases
cd /home/data/httpd/archive.eclipse.org/modeling/mdt/ocl/updates/releases
ant -f /shared/modeling/tools/promotion/manage-composite.xml add -Dchild.repository=5.0.5

Prepare the releases p2 repository

The former practice contributed the final RC-build to SimRel and performed a number of manual rename activities once the build was successful and ready to be published. These manual activities are hard now that the remote access to build.eclipse.org is more restricted.

There is now no need to prepare a releases area. Just perform an R-build with an alias of the release name. Do this as late as practical before the final SimREl build so that the R-build can be contributed to the SimRel aggregator.

Update the Help Info Center

The Help Info Center is now populated automatically.

With every release a bugzilla is created so that every project can publish where the doc plugin is located in the new release repository. We will usually need to keep an eye to the cross-project-issues mailing list to catch the proper bugzilla up (Following the cross-project dot inbox @at eclipse dot org bugzilla account may also help). In the corresponding Juno release bugzilla 379598 , you may find different examples about how to provide the required information.

Final Release Day

The R-build is automatically published, so no immediate action is required.

Update Eclipse Market Entry

The Eclipse OCL entry in the Eclipse MarketPlace requires to be updated with the final R-build:

Eclipse OCL at Market Place

Next Version

The Eclipse OCL entry in the Eclipse MarketPlace requires to be updated with the final R-build: The project should be moved onto the next release number by editing the many version numbers in MANIFEST.MF, pom.xml, feature.xml. Once this has been debugged using a local Tycho build, the Promoter job can be re-enabled.

Announcement

Remember to announce the new release in our public forum.