Milestone 0.6

Overall architecture, documentation, project management, deployment

  1. Automated daily builds of each Higgins component 157065

HBX

  1. Startup processing
    • Startup dialog (including user accept service TOS)
    • Background screen-scrape job processing
  2. Update the HBX doc (e.g. target protocols (e.g. OpenID), non-pluggable assumption)
  3. For RSS-P: RP site i-card issuance 152861
  4. OpenID-H support
    • Collaborate on OpenID 2.0 "-H" protocol extension
    • Begin implementation
  5. Begin work on i-names support

ISS

  1. ISS Web UI --begin initial implementation
  2. I-Card Selector Service (ISS) --API and initial implementation
  3. I-Card Registry --API and initial implementation
    • OpenID I-Card Provider
    • CardSpace I-Card Provider
    • RSS-P I-Card Provider
    • Persona I-Card Provider
  4. Token Issuer
    • Token Provider
      • SAML 1.1
      • Idemix
      • X509
      • Idemix token provider

IdAS

  1. IdAS Registry implementation [in progress]
  2. (153208) IdAS unit tests (.higgins.idas.test) [Waiting for factory instantiation mechanism]
  3. Start work on remote interfaces
  4. Context providers
    • (852856) Jena-based provider (uses HSQLDB) [80% done]
    • XML file-based provider [in progress]
    • LDAP-based provider [in progress]
  1. RP Enablement
    • Begin spec/scoping work