Difference between revisions of "Mihini/Project Plan"
< Mihini
(→Release calendar) |
|||
Line 1: | Line 1: | ||
− | |||
− | |||
= Introduction = | = Introduction = | ||
Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list. | Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list. | ||
Line 35: | Line 33: | ||
|- | |- | ||
| M1 | | M1 | ||
− | | | + | | 12-Apr-13 |
| 23-Aug-13 | | 23-Aug-13 | ||
| 21-Feb-14 | | 21-Feb-14 | ||
Line 50: | Line 48: | ||
|- style="font-weight:bold;" | |- style="font-weight:bold;" | ||
| final | | final | ||
− | | | + | | 24-May-13 |
| 6-Dec-13 | | 6-Dec-13 | ||
| 6-Jun-14 | | 6-Jun-14 |
Revision as of 05:38, 13 March 2013
Introduction
Please send comments about this plan to the mihini-dev@eclipse.org developer mailing list.
This document lays out the feature and API set for the feature releases of Mihini.
Release Deliverables
You can find more details on the Project Plan discussions for 0.8
Release plan
Mihini has a stable release every 6 month.
Every major release is maintained for 9 months:
- SR1 is "stable"+3 months,
- SR2 is "stable"+6 months,
- SR3 is "stable"+9 months.
Milestones allow to commit on delivering most priority features and bug fixes first, and move towards stabilization when reaching Release Candidates.
Release calendar
0.8 | 0.9 | 1.0 | |
---|---|---|---|
M1 | 12-Apr-13 | 23-Aug-13 | 21-Feb-14 |
M2 | *skipped* | 4-Oct-13 | 4-Apr-14 |
RC1 | 10-May-13 | 15-Nov-13 | 6-May-14 |
final | 24-May-13 | 6-Dec-13 | 6-Jun-14 |
Maintenance releases | |||
SR1 | 30-Aug-13 | TBD | TBD |
SR2 | 29-Nov-13 | TBD | TBD |
SR3 | 28-Feb-14 | TBD | TBD |