Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "MemoryAnalyzer/Ramp Down Plan"
m (→Ramp down plan) |
(→Ramp down plan) |
||
(5 intermediate revisions by the same user not shown) | |||
Line 4: | Line 4: | ||
For milestones, the component lead (or delegate) is enough to review and approve a bug. | For milestones, the component lead (or delegate) is enough to review and approve a bug. | ||
− | '''For M7, we plan to be API and feature complete''', so there will be no breaking API changes and no new feature requests will be accepted. | + | '''For M3 [''was M7 for Photon and before''], we plan to be API and feature complete''', so there will be no breaking API changes and no new feature requests will be accepted. |
− | '''For RC1 | + | '''For RC1 [''was RC1 and RC2 for Photon and before''] only bug fixes to Memory Analyzer''' functionality should be done. The following describes the types of bugs that would be appropriate: |
* A regression | * A regression | ||
* A P1 or P2 bug, one that is blocking or critical | * A P1 or P2 bug, one that is blocking or critical | ||
− | * Minor documentation changes | + | * Minor documentation changes, including adding new and noteworthy |
− | '''For RC3 - RC4''' only | + | '''For RC2 [''was RC3 - RC4 for Photon and before'']''' only bug fixes damaging the build/functionality of the simultaneous release should are allowed |
− | + | ||
− | + | ||
* [[Galileo Simultaneous Release]] | * [[Galileo Simultaneous Release]] | ||
* [[Helios Simultaneous Release]] | * [[Helios Simultaneous Release]] | ||
* [[Indigo Simultaneous Release]] | * [[Indigo Simultaneous Release]] | ||
+ | * [[Juno/Simultaneous Release Plan]] | ||
+ | * [[Kepler/Simultaneous Release Plan]] | ||
+ | * [[Luna/Simultaneous Release Plan]] | ||
+ | * [[Mars/Simultaneous Release Plan]] | ||
+ | * [[Neon/Simultaneous Release Plan]] | ||
+ | * [[Oxygen/Simultaneous Release Plan]] | ||
+ | * [[Photon/Simultaneous Release Plan]] | ||
+ | * [[Simultaneous Release]] subsequent releases on a 13-week cycle | ||
[[Category:Memory Analyzer]] | [[Category:Memory Analyzer]] |
Latest revision as of 05:12, 23 October 2019
Ramp down plan
Typically the last week of a Milestone is for testing, and fixing only regressions and P1 or blocking defects. For milestones, the component lead (or delegate) is enough to review and approve a bug.
For M3 [was M7 for Photon and before], we plan to be API and feature complete, so there will be no breaking API changes and no new feature requests will be accepted.
For RC1 [was RC1 and RC2 for Photon and before] only bug fixes to Memory Analyzer functionality should be done. The following describes the types of bugs that would be appropriate:
- A regression
- A P1 or P2 bug, one that is blocking or critical
- Minor documentation changes, including adding new and noteworthy
For RC2 [was RC3 - RC4 for Photon and before] only bug fixes damaging the build/functionality of the simultaneous release should are allowed
- Galileo Simultaneous Release
- Helios Simultaneous Release
- Indigo Simultaneous Release
- Juno/Simultaneous Release Plan
- Kepler/Simultaneous Release Plan
- Luna/Simultaneous Release Plan
- Mars/Simultaneous Release Plan
- Neon/Simultaneous Release Plan
- Oxygen/Simultaneous Release Plan
- Photon/Simultaneous Release Plan
- Simultaneous Release subsequent releases on a 13-week cycle