Work Items for Koneki LDT 1.0

Below are items that the Koneki team and the community at large think are worth being considered for the 1.0 release. This release is expected for the middle of 2013.

Schedule

Milestones   End Date          Kepler Targeted Milestones   Details         
M1           Friday, April 19  None                         All Features must be present in M1
RC1          Friday, May 03    M7  05/03 to 05/10           Time between M1 and RC1 should be used to do validation and bug fixes.  
RC2          Friday, May 24    RC3 05/24 to 05/31           Optional release to fix critical bugs and non intrusive bugs.
RC3          Friday, June 07   RC4 06/07 to 06/14           Optional release to fix critical bugs and non intrusive bugs.

see Kepler Schedule.

Features Lists

Lua 5.2 Support

Ok green.gif Debugger Support (375622)

Ok green.gif Shiped Interpreter (Based on JNLua 1.0) (401925)

Ok green.gif Shiped Execution Environment (401924)

Chkbox disabled.gif Support syntax of GOTO/LABEL (401928)

Ok green.gif Manage Default Execution Environement (386557)

Metalua

Progress.gif Host Metalua at eclipse.org (400321)

Progress.gif Integrate new Metalua version (401929)

Debugger

Ok green.gif Support LuaJIT 2.0.0 (398531)

Ok green.gif Support interpreter without -e option (390545)

AST

Progress.gif Use heuristics to extract more information from code (381671)

Bugzilla Requests

Project Plan : The bigs features we will try to deliver.

Bugs fixed : Bugs already fixed.

Bugs to fix : List of bugs and little improvements we will try to close.

To understand priorities and severities meaning : http://wiki.eclipse.org/Koneki/Development#Bugzilla_severity_and_priority