JWT Ramp-Down-Policy
Revision as of 06:51, 3 December 2008 by Mickael.istria.openwide.fr (Talk | contribs) (→Build Schedule)
Galileo
Build Schedule
- Offset: +3 (milestones 3 weeks after the platform milestones)
Date | Name | JWT Release |
---|---|---|
December 2008 | 0.6 JWT for Vendors | |
5th january 2008 | Galileo M4 + 3 | |
10th february 2008 | Galileo M5 + 3 | |
end of february 2009 | 0.7 JWT for SOA | |
19th march 2008 | Galileo M6 + 3 | |
april or may 2008 | 1.0 JWT for Users | |
6th may 2008 | Galileo M7 + 3 | |
Every wednesday from 20th may | Galileo RC n + 3 |
See also JWT Roadmap
Issues and bug fixing
Let's use bugs priority to find out which bugs are to save first for milestones and release:
- priority P1 means that the bug is to be fixed for next milestone
- priority P2 means that the bug is to be fixed before RC1
- Other priority are used for enhancements, new features and discussions
Thus, JWT is ready for Galileo when all P1 and P2 bugs are closed.