Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "Debug/Plan/3.8"
< Debug
(New page: {{warning|Unofficial Planning Document|This is an unofficial document used by the Debug team to help with the planning process. Items on this list are not guaranteed to be found in a relea...) |
m |
||
Line 19: | Line 19: | ||
{{PlanItem|Prepare 3.7.2 Fixes||Investigate}} | {{PlanItem|Prepare 3.7.2 Fixes||Investigate}} | ||
− | === M6 - March | + | === M6 - March (API Freeze) === |
− | === M7 - April | + | === M7 - April (Feature Freeze) === |
{{PlanItem|Bug fixing||Investigate}} | {{PlanItem|Bug fixing||Investigate}} |
Revision as of 16:44, 7 July 2011
Contents
Schedule
Dates are listed in the Eclipse Platform Releng Calendar (view as iCal). Note that some work items will take longer than one milestone to complete. Plan items are listed in the milestone when work is intended to start on the item.
M1 - August
M2 - September
M3 - October
M4 - December
M5 - January
M6 - March (API Freeze)
M7 - April (Feature Freeze)
RC Builds
Unplanned Items
This section will list items that we are interested in completing during 3.8 but have not been scheduled.