Difference between revisions of "DTP PMC Meeting, August 19, 2008"

(Agenda)
Line 22: Line 22:
 
**September 5 (SH time) build will be the RC2 integration build. Test on September 5 & September 8, rebuild if issues arise
 
**September 5 (SH time) build will be the RC2 integration build. Test on September 5 & September 8, rebuild if issues arise
 
**Just testing after that until September 16
 
**Just testing after that until September 16
 +
*Galileo planning [DTP/DTP_Galileo_Plan_Draft]
  
 
*Open discussion
 
*Open discussion

Revision as of 14:22, 18 August 2008

Back to DTP PMC Meeting Page

Attendees

  • Brian Fitzpatrick
  • Linda Chan
  • John Graham
  • Sheila Sholars

Regrets

Agenda

  • 1.6.1 Rampdown policy
    • M2 is August 25, 2008
    • Ganymede SR1 release train as a +1 project. Those dates are [[here].
      • September 2, 2008 - RC1
      • September 9, 2008 - RC2
      • September 16, 2008 - RC3 (Final Release, available September 24, 2008)
  • Proposed policy:
    • Open for fixes until afternoon of August 25, 2008 (SH time)
    • Team lead approval needed for any fixes the week of August 25 - August 28
    • August 29 (SH time) build will be the RC1 integration build. Test on August 29 & September 1, rebuild if issues arise
    • Week of September 1 - September 4, PMC approval required (reasons, implications, testing, patch)
    • September 5 (SH time) build will be the RC2 integration build. Test on September 5 & September 8, rebuild if issues arise
    • Just testing after that until September 16
  • Galileo planning [DTP/DTP_Galileo_Plan_Draft]
  • Open discussion

Minutes

Action Items

Tabled for Later Discussion