DTP Ganymede Milestone Sign-off Policy
Revision as of 13:46, 7 December 2007 by John.graham.sybase.com (Talk | contribs)
Status
[12/7/07]: This document is a draft and has not been approved by the DTP PMC.
Introduction
As both an Eclipse project and a member of coordinated releases (Callisto, Europa, Ganymede), it is imperative that DTP milestones, release candidates, and releases are of acceptable quality.
Process
- For each DTP milestone, release candidate and release date, the PMC will determine a "candidate build" date on which the associated DTP build will be taken as the testing target.
- For each DTP milestone, release candidate and release date, the PMC will determine a sign-off close date and publish it to the dtp-pmc mailing list.
- Each DTP project lead should work with their teams to test the DTP candidate build.
- By the sign-off close date, each DTP project lead will send an email to dtp-pmc expressing one of the following sign-off options: