Difference between revisions of "DTP 1.5 Rampdown Policy"

Line 8: Line 8:
  
 
==Rampdown Cycles==
 
==Rampdown Cycles==
 +
 +
===May 11: DTP 1.5RC0===
 +
*Monday, May 14, through Friday, May 18: Testing pass
 +
*Monday, May 21, through Friday, May 25: Fix pass. All bugs must be approved by project lead, who must post bug list to [mailto:dtp-dev@eclipse.org dtp-dev].

Revision as of 13:04, 27 February 2007

Back to DTP Main Page

Status

2/27: This document is a draft and has not been reviewed/approved by the PMC.

Purpose

This document defines a set of rampdown cycles for DTP 1.5. The goal is to ensure that DTP stability and completeness converges on the 1.5 release dates, while allowing mechanisms for changes as necessary. Since this document is about the rampdown, only cycles post DTP 1.5RC0 will be detailed below.

Rampdown Cycles

May 11: DTP 1.5RC0

  • Monday, May 14, through Friday, May 18: Testing pass
  • Monday, May 21, through Friday, May 25: Fix pass. All bugs must be approved by project lead, who must post bug list to dtp-dev.