Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "Callisto Plan Summary"

(Everthing In A Table)
Line 41: Line 41:
 
| align="center" | RC2
 
| align="center" | RC2
 
| align="center" | RC3
 
| align="center" | RC3
| colspan="4" align="center" | RC4
+
| align="center" | RC4
 +
| colspan="4" align="center" | RC5
 
|-
 
|-
 
| <b>EMF</b>
 
| <b>EMF</b>
Line 122: Line 123:
  
 
* 2-Jun - Platform (RC7)
 
* 2-Jun - Platform (RC7)
* 19-Jun - CDT (RC3) , DTP(RC4 planned, RC5 if needed), EMF (RC7), GEF (RC5), VE (RCx, none planned)
+
* 19-Jun - CDT (RC3) , DTP(RC5), EMF (RC7), GEF (RC5), VE (RCx, none planned)
 
* 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
 
* 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
 
* 22-Jun - admin, mirror propagation
 
* 22-Jun - admin, mirror propagation

Revision as of 16:57, 30 May 2006

This is summary table of the Callisto Plan

The primary purpose of this summary is to provide one place to see the correlations of the Callisto release candiate names and dates and the participating projects release candidate names and dates. The participating projects may update this page to reflect current status and plans.

Everthing In A Table

Callisto
RC1a RC2 RC3 RC4 RC5 RC6 GA
BIRT RC0 RC2 RC3 RC4 RC5 RC6
CDT RC0 RC1 RC2 RC3
DTP RC1 RC2 RC3 RC4 RC5
EMF RC1 RC2a RC4 RC6 RC7
GEF RC0 RC2 RC3 RC4 RC5
GMF RC0 RC2 RC3 RC4 RC5 RC6
Platform RC1a RC2 RC4 RC6 RC7
TPTP i2 i3 i4
WTP RC1a RC2 RC3 RC4 RC5 RC6
VE M3 RC1 RC2

RC1a (25-Apr)

  • 14-Apr - Platform (RC1a)
  • 19-Apr - CDT, DTP(RC1), EMF (RC1) , GEF (RC0), VE (M3)
  • 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
  • 25-Apr - admin, mirror propagation

RC2 (9-May)

  • 28-Apr - Platform (RC2)
  • 3-May - CDT (RC0), DTP(RC2), EMF (RC2a) , GEF (RC2), VE (M3)
  • 5-May - BIRT(RC2), GMF (RC2), TPTP (RC2), WTP (RC2)
  • 9-May - admin, mirror propagation

RC3 (23-May)

  • 12-May - Platform (RC4)
  • 17-May - CDT (RC1), DTP(RC3), EMF (RC4), GEF (RC3), VE (RC1)
  • 19-May - BIRT(RC3), GMF (RC3), TPTP (RC2), WTP (RC3)
  • 23-May - admin, mirror propagation

RC4 (2 -Jun)

  • 26-May - Platform (RC6)
  • 29-May - CDT (RC2), DTP(RC4), EMF (RC6), GEF (RC4), VE (RC2)
  • 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
  • 2 -June - admin, mirror propagation

RC5 (22-Jun)

  • 2-Jun - Platform (RC7)
  • 19-Jun - CDT (RC3) , DTP(RC5), EMF (RC7), GEF (RC5), VE (RCx, none planned)
  • 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
  • 22-Jun - admin, mirror propagation

RC6 (30-Jun)

  • 28-Jun - Platform (RCx, none planned)
  • 28-Jun - CDT (RC4, if needed) , DTP(RCx, none planned), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
  • 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
  • 30-Jun - admin, mirror propagation

Callisto Release 6/30