Skip to main content

Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.

Jump to: navigation, search

Difference between revisions of "Callisto Plan Summary"

(RC4 (2 -Jun))
(RC5 (22-Jun))
Line 40: Line 40:
  
 
* 16-Jun - Platform (RCx, none planned)
 
* 16-Jun - Platform (RCx, none planned)
* 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF, GEF (RC5), VE
+
* 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF, GEF (RC5), VE (RCx, none planned)
 
* 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
 
* 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
 
* 22-Jun - admin, mirror propagation
 
* 22-Jun - admin, mirror propagation

Revision as of 12:11, 2 May 2006

This is summary table of the Callisto Plan

The primary purpose of this summary is to provide one place to see the correlations of the Callisto release candiate names and dates and the participating projects release candidate names and dates. The participating projects may update this page to reflect current status and plans.


RC1a (25-Apr)

  • 14-Apr - Platform (RC1a)
  • 19-Apr - CDT, DTP(RC1), EMF (RC1) , GEF (RC0), VE (M3)
  • 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
  • 25-Apr - admin, mirror propagation

RC2 (9-May)

  • 28-Apr - Platform (RC2)
  • 3-May - CDT (RC0), DTP(RC2), EMF (RC2) , GEF (RC2), VE (M3)
  • 5-May - BIRT(RC2), GMF (RC2), TPTP (i2), WTP (RC2)
  • 9-May - admin, mirror propagation

RC3 (23-May)

  • 12-May - Platform (RC4)
  • 17-May - CDT (RC0), DTP(RC3), EMF (RC4), GEF (RC3), VE (RC1)
  • 19-May - BIRT(RC3), GMF (RC3), TPTP (i2), WTP (RC3)
  • 23-May - admin, mirror propagation

RC4 (2 -Jun)

  • 26-May - Platform (RCx, none planned)
  • 29-May - CDT (RC1), DTP(RC4), EMF, GEF (RC4), VE (RCx, none planned)
  • 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
  • 2 -June - admin, mirror propagation

RC5 (22-Jun)

  • 16-Jun - Platform (RCx, none planned)
  • 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF, GEF (RC5), VE (RCx, none planned)
  • 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
  • 22-Jun - admin, mirror propagation

RC6 (30-Jun)

  • 28-Jun - Platform (RCx, none planned)
  • 28-Jun - CDT (RC2, if needed) , DTP(RCx, none planned), EMF, GEF (RC5), VE
  • 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
  • 30-Jun - admin, mirror propagation

Callisto Release 6/30

Back to the top