This is a temporaray working copy of what is proposed to be the summary table of the Callisto
+
This is summary table of the [http://www.eclipse.org/projects/callisto.php Callisto Plan]
Plan as detailed in http://www.eclipse.org/projects/callisto.php
+
 
 +
The primary purpose of this summary is to provide
 +
one place to see the correlations of the Callisto
 +
release candiate names and dates and the participating projects
 +
release candidate names and dates. The participating projects may
 +
update this page to reflect current status and plans.
  
  

Revision as of 17:28, 1 May 2006

This is summary table of the Callisto Plan

The primary purpose of this summary is to provide one place to see the correlations of the Callisto release candiate names and dates and the participating projects release candidate names and dates. The participating projects may update this page to reflect current status and plans.


RC1a (25-Apr)

  • 14-Apr - Platform (RC1a)
  • 19-Apr - CDT, DTP(RC1), EMF (RC1) , GEF (RC0), VE
  • 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
  • 25-Apr - admin, mirror propagation

RC2 (9-May)

  • 28-Apr - Platform (RC2)
  • 3-May - CDT (RC0), DTP(RC2), EMF (RC2) , GEF (RC2), VE
  • 5-May - BIRT(RC2), GMF (RC2), TPTP (i2), WTP (RC2)
  • 9-May - admin, mirror propagation

RC3 (23-May)

  • 12-May - Platform (RC4)
  • 17-May - CDT (RC0), DTP(RC3), EMF (RC4), GEF (RC3), VE
  • 19-May - BIRT(RC3), GMF (RC3), TPTP (i2), WTP (RC3)
  • 23-May - admin, mirror propagation

RC4 (2 -Jun)

  • 26-May - Platform (RCx, none planned)
  • 29-May - CDT (RC1), DTP(RC4), EMF, GEF (RC4), VE
  • 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
  • 2 -June - admin, mirror propagation

RC5 (22-Jun)

  • 16-Jun - Platform (RCx, none planned)
  • 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF, GEF (RC5), VE
  • 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
  • 22-Jun - admin, mirror propagation

RC6 (30-Jun)

  • 28-Jun - Platform (RCx, none planned)
  • 28-Jun - CDT (RC2, if needed) , DTP(RCx, none planned), EMF, GEF (RC5), VE
  • 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
  • 30-Jun - admin, mirror propagation

Callisto Release 6/30