Difference between revisions of "Callisto Plan Summary"
Line 42: | Line 42: | ||
* 28-Jun - Platform (RCx, none planned) | * 28-Jun - Platform (RCx, none planned) | ||
− | * 28-Jun - CDT (RC2) , DTP, EMF, GEF (RC5), VE | + | * 28-Jun - CDT (RC2, if needed) , DTP, EMF, GEF (RC5), VE |
* 28-Jun - BIRT, GMF, TPTP (RC6), WTP (RC6) | * 28-Jun - BIRT, GMF, TPTP (RC6), WTP (RC6) | ||
* 30-Jun - admin, mirror propagation | * 30-Jun - admin, mirror propagation | ||
=== Callisto Release 6/30 === | === Callisto Release 6/30 === |
Revision as of 12:41, 26 April 2006
This is a temporaray working copy of what is proposed to be the summary table of the Callisto Plan as detailed in http://www.eclipse.org/projects/callisto.php
Contents
RC1 (25-Apr)
- 14-Apr - Platform (RC1a)
- 19-Apr - CDT, DTP, EMF (RC1) , GEF (RC0), VE
- 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
- 25-Apr - admin, mirror propagation
RC2 (9-May)
- 28-Apr - Platform (RC2)
- 3-May - CDT (RC0), DTP, EMF (RC2) , GEF (RC2), VE
- 5-May - BIRT, GMF, TPTP (i2), WTP (RC2)
- 9-May - admin, mirror propagation
RC3 (23-May)
- 12-May - Platform (RC4)
- 17-May - CDT (RC0), DTP, EMF (RC4), GEF (RC3), VE
- 19-May - BIRT, GMF, TPTP (i2), WTP (RC3)
- 23-May - admin, mirror propagation
RC4 (2 -Jun)
- 26-May - Platform (RCx, none planned)
- 29-May - CDT (RC1), DTP, EMF, GEF (RC4), VE
- 31-May - BIRT, GMF, TPTP (i3), WTP (RC4)
- 2 -June - admin, mirror propagation
RC5 (22-Jun)
- 16-Jun - Platform (RCx, none planned)
- 19-Jun - CDT (RC1) , DTP, EMF, GEF (RC5), VE
- 20-Jun - BIRT, GMF, TPTP (RC5), WTP (RC5)
- 22-Jun - admin, mirror propagation
RC6 (30-Jun)
- 28-Jun - Platform (RCx, none planned)
- 28-Jun - CDT (RC2, if needed) , DTP, EMF, GEF (RC5), VE
- 28-Jun - BIRT, GMF, TPTP (RC6), WTP (RC6)
- 30-Jun - admin, mirror propagation