Difference between revisions of "Callisto Plan Summary"

(RC4 (2 -Jun))
(RC6 (30-Jun))
Line 47: Line 47:
  
 
* 28-Jun - Platform (RCx, none planned)
 
* 28-Jun - Platform (RCx, none planned)
* 28-Jun - CDT (RC2, if needed) , DTP(RCx, none planned), EMF, GEF (RC5), VE (RCx, none planned)
+
* 28-Jun - CDT (RC2, if needed) , DTP(RCx, none planned), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
 
* 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
 
* 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
 
* 30-Jun - admin, mirror propagation
 
* 30-Jun - admin, mirror propagation
  
 
=== Callisto Release 6/30 ===
 
=== Callisto Release 6/30 ===

Revision as of 13:03, 3 May 2006

This is summary table of the Callisto Plan

The primary purpose of this summary is to provide one place to see the correlations of the Callisto release candiate names and dates and the participating projects release candidate names and dates. The participating projects may update this page to reflect current status and plans.


RC1a (25-Apr)

  • 14-Apr - Platform (RC1a)
  • 19-Apr - CDT, DTP(RC1), EMF (RC1) , GEF (RC0), VE (M3)
  • 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
  • 25-Apr - admin, mirror propagation

RC2 (9-May)

  • 28-Apr - Platform (RC2)
  • 3-May - CDT (RC0), DTP(RC2), EMF (RC2) , GEF (RC2), VE (M3)
  • 5-May - BIRT(RC2), GMF (RC2), TPTP (i2), WTP (RC2)
  • 9-May - admin, mirror propagation

RC3 (23-May)

  • 12-May - Platform (RC4)
  • 17-May - CDT (RC0), DTP(RC3), EMF (RC4), GEF (RC3), VE (RC1)
  • 19-May - BIRT(RC3), GMF (RC3), TPTP (i2), WTP (RC3)
  • 23-May - admin, mirror propagation

RC4 (2 -Jun)

  • 26-May - Platform (RCx, none planned)
  • 29-May - CDT (RC1), DTP(RC4), EMF (RCx, none planned), GEF (RC4), VE (RCx, none planned)
  • 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
  • 2 -June - admin, mirror propagation

RC5 (22-Jun)

  • 16-Jun - Platform (RCx, none planned)
  • 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
  • 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
  • 22-Jun - admin, mirror propagation

RC6 (30-Jun)

  • 28-Jun - Platform (RCx, none planned)
  • 28-Jun - CDT (RC2, if needed) , DTP(RCx, none planned), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
  • 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
  • 30-Jun - admin, mirror propagation

Callisto Release 6/30