COSMOS ME Minutes 09SEP08
Revision as of 10:52, 15 September 2008 by Jason.losh.sas.com (Talk | contribs) (New page: == Logistics == * Date: 09SEP08 * Time: 11AM EST * Attendees: Charlie Halloran, Eric Rose, Yan Zhao, Brad Beck, Robert DeMason, Josh Hester, Mark McCraw, Jeff Hamm, Merri Jensen, Jason Los...)
Logistics
- Date: 09SEP08
- Time: 11AM EST
- Attendees: Charlie Halloran, Eric Rose, Yan Zhao, Brad Beck, Robert DeMason, Josh Hester, Mark McCraw, Jeff Hamm, Merri Jensen, Jason Losh
Minutes
- Administrative
- Update on SAS participation
- Jason gave update that Robert will be leaving the team. New participant (tbd) from SAS will replace him.
- i13 testing status
- Tooling update (Eric/Chris/Yan/Josh/Robert)
- Scoping for i14 is underway - target completion 16SEP
- BTG status (Josh/Robert)
- Working on TPTP tests for rules submitted in i13
- Change analyzer update (Merri)
- Continuing to work through this. Making slow but steady progress.
- Runtime update (Jeff)
- Change resolver design is in progress