Notice: this Wiki will be going read only early in 2024 and edits will no longer be possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
Difference between revisions of "COSMOS 1.1 Iteration5 Features"
(→Bugzillas for this iteration (Jimmy, David, Jason, Saurabh, QA, Doc, Ruth)) |
(→Bugzillas for this iteration (Jimmy, David, Jason, Saurabh, QA, Doc, Ruth)) |
||
Line 101: | Line 101: | ||
<td>Enhancement</td> | <td>Enhancement</td> | ||
<td>Connect CLIAdapter to SDD Runtime Orchestrator</td> | <td>Connect CLIAdapter to SDD Runtime Orchestrator</td> | ||
+ | <td></td> | ||
+ | <td>Jeff Hamm</td> | ||
+ | <td>High</td> | ||
+ | <td>N/A</td> | ||
+ | <td>N/A</td> | ||
+ | </tr> | ||
+ | |||
+ | <tr> | ||
+ | <td>High</td> | ||
+ | <td> <font color="green">On track</font> </td> | ||
+ | <td>Management Enablement</td> | ||
+ | <td>[https://bugs.eclipse.org/bugs/show_bug.cgi?id=275673 275673 ]</td> | ||
+ | <td>Normal</td> | ||
+ | <td>Refactor the advisor bundle to move the CLI</td> | ||
<td></td> | <td></td> | ||
<td>Jeff Hamm</td> | <td>Jeff Hamm</td> |
Revision as of 11:10, 11 May 2009
Contents
COSMOS v1.1 iteration 5 plan
Schedule for Iteration 5
Design doc every enhancement
- if the enhancement is really small, put in at least a paragraph and a link to the use case for QA and documentation.
- if the enhancement is not small, the design doc needs to explain the change, anyone other than the assignee who is affected, how much work it is, any ramifications, and in general please avoid any changes to 3rd party materials other than removing a dependency on it. We have no guarantee that the change will be approved for COSMOS v1.1.
Bugzillas for this iteration (Jimmy, David, Jason, Saurabh, QA, Doc, Ruth)
Sizing legend:
- Low - takes 1-3 days
- Medium - takes a week
- High - takes more than a week
Status to be filled in by:
- Data Collection bugzilla status (Jimmy Mohsin)
- Data Visualization bugzilla status (Jimmy Mohsin)
- Resource Modeling bugzilla status (David Whiteman)
- Management Enablement bugzilla status (Jason Losh)
- RE/Build bugzilla status (Saurabh Dravid)
- QA bugzilla status (No owner)
- Doc bugzilla status (No owner)
- Legal & release review prep and status (Ruth Lee)
The Status column can have one of these values:
- COMPLETE
- On track
- At risk
- Not containable
- Defer (no longer a priority for this iteration)
- Not started
Priority | Status | Project or subteam | Enhancement | Severity | Description | Blocked by (if applicable) | Owner | Sizing | Design Doc | Use Case |
---|---|---|---|---|---|---|---|---|---|---|
P1 | All | 259011 | Normal | Prep for the V1.1 release (complete) | Ruth Lee | N/A | N/A | N/A | ||
High | On track | Management Enablement | 273067 | Enhancement | Refactor op/installer as OSGi bundle | Ed Blackman | High | N/A | N/A | |
High | On track | Management Enablement | 274067 | Defect | Update targetResourceRef attribute in COSMOS SDD | Jason Losh | High | N/A | N/A | |
High | On track | Management Enablement | 275669 | Enhancement | Connect CLIAdapter to SDD Runtime Orchestrator | Jeff Hamm | High | N/A | N/A | |
High | On track | Management Enablement | 275673 | Normal | Refactor the advisor bundle to move the CLI | Jeff Hamm | High | N/A | N/A | |