COSMOS v1.1 iteration 1 plan

Schedule for Iteration 1

Schedule for Iteration 1

Design doc every enhancement

  • if the enhancement is really small, put in at least a paragraph and a link to the use case for QA and documentation.
  • if the enhancement is not small, the design doc needs to explain the change, anyone other than the assignee who is affected, how much work it is, any ramifications, and in general please avoid any changes to 3rd party materials other than removing a dependency on it. We have no guarantee that the change will be approved for COSMOS v1.1.

Bugzillas for this iteration (Jimmy, David, Jason, Saurabh, QA, Doc, Ruth)

Sizing legend:

  • Low - takes 1-3 days
  • Medium - takes a week
  • High - takes more than a week

Status to be filled in by:

  • Data Collection bugzilla status (Jimmy Mohsin)
  • Data Visualization bugzilla status (Jimmy Mohsin)
  • Resource Modeling bugzilla status (David Whiteman)
  • Management Enablement bugzilla status (Jason Losh)
  • RE/Build bugzilla status (Saurabh Dravid)
  • QA bugzilla status (No owner)
  • Doc bugzilla status (No owner)
  • Legal & release review prep and status (Ruth Lee)

The Status column can have one of these values:

  • COMPLETE
  • On track
  • At risk
  • Not containable
  • Defer (no longer a priority for this iteration)
  • Not started

Note: there are no known features in plan for iteration 1 for the Resource Modeling, Data Collection, or Data Visualization components. Resource Modeling will have several small defect fixes in the iteration.


Priority Status Project or subteam Enhancement Severity Description Blocked by (if applicable) Owner Sizing Design Doc Use Case
Medium COMPLETE ME 257992 Enhancement Rule to merge AlternativeRequirementType from two or more SDDs Josh Hester Low [1] [2]
Medium COMPLETE ME 257993 Enhancement Rule to merge AlternativeRequiredBaseConstraints from two or more SDDs Josh Hester Low [3] [4]
Medium COMPLETE ME 257994 Enhancement Rule to merge PropertyValueLists from two or more SDDs Josh Hester Low [5] [6]
Medium COMPLETE ME 257995 Enhancement Rule to merge RequiredBases from two or more SDDs Josh Hester Low [7] [8]
Medium COMPLETE ME 257996 Enhancement Rule to merge RequiredBaseConstraints from two or more SDDs Josh Hester Low [9] [10]
Medium COMPLETE ME 257997 Enhancement Rule to merge CompletionTypes from two or more SDDs Josh Hester Low [11] [12]
Medium COMPLETE ME 257998 Enhancement Rule to merge AdditionalContents from two or more SDDs Josh Hester Low [13] [14]
Medium COMPLETE All 258998 Defect Update the IP log and about.html in v1.1 iteration 1 Ruth Lee N/A N/A N/A
Low COMPLETE ME 257984 Major COSMOS 1.1.0 build failing Josh Hester
Low COMPLETE RE 259016 Normal Automate SDD junit test cases Saurabh Dravid

Use cases