BIRT2.5 Rampdown Policy

Revision as of 02:05, 6 January 2009 by Xgu.actuate.com (Talk | contribs) (Purpose)

Purpose

This document describes a set of ramp down rules for the BIRT 2.5 Release. The Builds and Release decisions occurs on the dates listed for each Release Candidate

Date

May 6 : BIRT 2.3 RC0

Through May 4, Testing and Fix pass.
Monday May 5 : BIRT 2.3 RC0 Candidate build
Monday May 5 until Tuesday May 6: RC0 Candidate testing. Ganymede update site update.
Tuesday May 6 until Wednesday May 7: Candidate build repackage with WTP RC0 and vote for the candidate build.


May 20 : BIRT 2.3 RC1

Through May 18, Testing and Fix pass.
Monday May 19 : BIRT 2.3 RC1 Candidate build
Monday May 19 until Tuesday May 20: RC1 Candidate testing. Ganymede update site update.
Tuesday May 20 until Wednesday May 21: Candidate build repackage with WTP RC1 and vote for the candidate build.


May 27 : BIRT 2.3 RC2

Tuesday May 20 through May 25, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday May 26 : BIRT 2.3 RC1 Candidate build
Monday May 26 until Tuesday May 27: RC1 Candidate testing. Ganymede update site update.
Tuesday May 27 until Wednesday May 28: Candidate build repackage with WTP RC2 and vote for the candidate build.


June 3 : BIRT 2.3 RC3

Tuesday May 27 through June 1, Testing and Fix pass. All Bug fixes must be approved by a Project Lead.
Monday Jun 2: BIRT 2.3 RC3 Candidate build
Monday Jun 2 until Tuesday June 3: RC3 Candidate testing. Ganymede update site update.
Tuesday Jun 3 until Wednesday Jun 4: Candidate build repackage with WTP RC3 and vote for the candidate build.


June 10: BIRT 2.3 RC4

Thursday June 3 through Tuesday June 8 Testing and Fix pass. All Bug fixes must be approved by the at least two project leads and BIRT PMC
Wednesday June 9: BIRT 2.3 RC4 Candidate build
Wednesday June 9 until Thursday June 10: RC4 Candidate testing. Ganymede update site update.
Tuesday Jun 10 until Wednesday Jun 11: Candidate build repackage with WTP RC4 and vote for the candidate build.


Post BIRT BIRT 2.3 RC4 through Ganymede Release

Tuesday June 10 until Tuesday June 17 (Ganymede Release): Testing Pass

Additional RC Builds will be scheduled as necessary