2007-01-11
Revision as of 14:39, 11 January 2007 by Cbrealey.ca.ibm.com (Talk | contribs)
WTP Development Status Meeting 2007-01-11
Outline
Attendees
Announcements and Reminders
WTP 1.5.3
WTP 2.0
Other business?
Team Status and Focus
- Attendees
- Announcements and Reminders
- Conferences:
- EclipseCon2007 open for short talk and demo (Jan 15) submissions.
- EclipseWorld2007, 11/6/2007-11/8/2007 in Reston, VA. The deadline for abstracts is 4/17/2007.
- Reminder:
- When you reject a hot bug request as a hot bug, change the summary to [hotbug_declined].
- When requested, be sure to update the smoke test results status page.
- Nominations are open for the Eclipse community awards.
- Announcements:
- Welcome to Pieter Humphrey, taking over for Lawrence Mandel!
- The issues with Eclipse CVS and downloads sites seem to be resolved.
- WTP 1.5.3
- Due: 2007-02-16
- 1/11 - Component leads complete triage scrub of targetted defects.
- 1/26 - WTP PMC review and approval will begin for any changes.
- 2/2 - Release candidates available for testing.
- 2/5-2/9 - Test and Defect Verifications - No more changes after 2/9.
- 2/12 - Zips and update site files ready to start the mirror process.
- 2/16 - Join Callisto Winter Maintenance Release availability.
- 1.5.3 Guidelines for fixes
- We will be declaring a 1.5.3M build this week, so please smoke test and report results using the latest 1.5.3 M build.
- Smoke Test Scenarios
- Please publish your smoke test scenarios by adding a link here.
- Bug lists
- Resolved, Unverified (~325)
- Verified, Not closed (~20)
- 1.5.3 Hot Bug Requests (~0)
- 1.5.3 Hot Bugs (~2)
- Blockers, Criticals (~1)
- Remaining 1.5.3 Targeted Defects (~49)
- WTP 2.0
- Build Status - David?
- Any news on Update Manager issues?
- Component Leads - Other remaining to do for M4 is the new and noteworthy section. Tim W to follow up with Pieter on creating a skeleton page with sections for each component to fill in. Pieter?
- M5 Proposed Plan
January 2007 - February 2007 Monday Tuesday Wednesday Thursday Friday 08
M5 Planning09
M5 Planning10
M5 Planning11
Status Call
Smoke Test12
Declare I Build15
M5 Development16
M5 Development17
M5 Development18
Status Call
Smoke Test19
Declare I Build22
M5 Development23
M5 Development24
M5 Development25
Status Call
Smoke Test26
Declare I Build29
M5 Development30
M5 Development31
M5 Development01
Status Call
Smoke Test02
Declare I Build05
M5 Development06
M5 Development07
M5 Development08
Status Call
Smoke Test09
Declare I Build
Platform M512
M5 Development
Start component lead change approval13
M5 Development14
M5 Development15
Status Call
Smoke Test16
Declare I Build
EMF M5
Write tests and produce FVT driver19
FVT and Compatibility Tests20
Defect Verifications
Mustfix defects21
Defect Verifications
Mustfix defects22
Defect Verifications
Status Call
Thumbs Up Test23
Declare WTP 2.0 M5
- Remaining Europa Timeline
January 2007 - February 2007 Platform +1 WTP M5 Feb 09 Feb 16 Feb 23 M6 - API Freeze Mar 23 Mar 30 Apr 06 M7 - RC0 May 04 May 11 May 18 RCn... RCX Jun 15 ? ? Europa Jun 29 Jun 29 Jun 29
- Smoke Test Scenarios
- Please publish your smoke test scenarios by adding a link here.
- Compatibility Tests for WTP 1.5 <--> WTP 2.0
- Information on what to test and how to publish your compatibility test plans can be found here.
- Only web services has entered this information, so we will start collecting status from each component next week.
- A JUnit test is fine, but please explain what the JUnit does. These tests only need to be run during milestion test passes.
- Performance and API Tests
- Need to investigate re-enabling these tests for M5. We will publish these results with every weekly declared build.
- Usage Reports
- The Adopter Usage Reports are posted for component owners...
- To ensure no one is using code they should not be using.
- To prioritize which code you plan to make API.
- The Extension Point Usage Reports are also posted. The instructions for adopters on how to contribute can be found here.
- Rob F to follow up for BEA to contribute these reports.
- Stay tuned in M5 for automated test coverage report numbers based on using TPTP's line coverage analysis tools. Also investigating cross referencing the data from the usage reports to detail where test coverage must be improved.
- Bug lists
- Untriaged (~50) Good progress, but still too many.
- Resolved, Unverified (~160)
- Resolved, Remind or Later (~37)
- Verified, Not closed (~23)
- 2.0 Hot Bug Requests (~0)
- 2.0 Hot Bugs (~0)
- Blockers, Criticals (~1)
- Other business?
- Java EE 5 Update - Chuck?
- There is a wiki page established for people to follow along.
- Website Update - Bob F?
Teams Status and Focus for Coming Week
- Common Component Team
- Server Component Team
- Datatools (RDB, 1.5.x only)
- XML/JSP Component Team
- Web Services Component Team
- WTP 1.5.3 - Fixing bugs and ongoing triage of bugs into and out of the release (Query). Today's count: 17.
- WTP 2.0 - Ongoing triaging of RFEs for inclusion in the plan.
- M4 - Smoke, function and compatibility test completed.
- Apache Axis2 - The Axis2 integration effort is in progress. See RFE 165664. Bi-weekly meetings continue. Use cases and requirements drafted. Secondary RFEs are open and targetted to M5 or M6. Lahiru Sandakith (WSO2) has developed and attached the first round of new plugins for Axis2. Legal and technical review commencing.
- Eclipse 3.3 - We are interested in contributing Eclipse WTP's Internet Preference Page to the Eclipse platform under RFE [154100 (Platform level proxy settings) https://bugs.eclipse.org/bugs/show_bug.cgi?id=154100].
- Eclipsecon 2007
- Three proposals submitted by the Web services team:
- Web Services tools in IBM Rational Application Developer v7.0 - DECLINED.
- Understanding the Web services development platform - a case study on adding the Apache Axis2 Web services runtime in WTP - DECLINED.
- Introduction to Web Services Tools in WTP - ACCEPTED. We will approach Christopher Judd for interest in collaborating with him on his similar proposal, Consuming and producing web services with Web Tools (WTP).
- We are submitting an Eclipse/Apache Axis2 demo.
- Three proposals submitted by the Web services team:
- Java EE Component Team
- Evaluate and refine initial design and code for functionality that supports attribute-based mapping of Java classpath entries into the virtual component tree.
- Dali JPA
- Held Dali 1.0 planning and design meetings 8th-10th - Dali_1.0_Planning_and_Design_meetings:_Monday_Jan._7th-8th
- Continue work on JPA model and M5 objectives (see link above for M5 plans)
- JSF
- DTP
- ATF
- releng
- Add versions 1.5.1,1.5.2,1.5.3 to the WTP bugzilla version options list when opening new bugs
- Investigating running and publishing the automated test coverage reports
- Investigating running Performance and API tests