Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
TPTP-AG-20080407
Revision as of 13:36, 7 April 2008 by Unnamed Poltroon (Talk)
Contents
Date
- April 7, 2008
Attendees
- Present:
- Oliver Cole
- Tony Wang
- Mikhail Voronin
- Joanna Kubasta
- Joel Cayne
- Eugene Chan
- Chris Elford
Topic
- Bugzilla Component Reorganization
Minutes
Finalizing I6
- Decision to patch the following defects into the 4.5 I6 candidate driver and release before EOD:
- The critical/blocker following defects cannot be contained in I6:
- Platform Project:
- Test Project:
- Joanna will communicate the limitations of the deferred I6 critical/blocker defects to the IBM consuming products impacted by these regressions.
- Paul will add release notes to the 4.5 Release Notes.
Bugzilla Component Reorganization
- Continuation of the Component Assignments to Projects topic at the March 2008 TPTP F-2-F.
- Review of the association of Bugzilla components (and their associated plug-ins) to projects.
- The Platform Project traditionally contained components used by one or more of the other projects (e.g. models).
- However, this is problematic due to the number of components used by one or more of the other projects, causing the Platform Project to excessively large.
- For example, the Trace views are contained in the Platform project since the intent was for reuse in all three projects but really only resourced and used in the Trace Project.
- Also, resourcing is not aligned well by components and projects.
- For example, Alex A. leads the Trace Project with IBM resources and Joanna leads the Platform Project with Intel resources but Alex A.'s focus is the tracing components.
- However, this is problematic due to the number of components used by one or more of the other projects, causing the Platform Project to excessively large.
- Project Leads were asked to create a proposal for items that should be under their project. For example, what project should own the Probekit?
- Platform Project: Outstanding.
- Test Project: No potential components to be changed, other than test models that may be separated into Test Project-specific plug-ins.
- Trace Project: Not represented.
- Monitoring Project: Not represented.
- We will keep the original four-project structure, but the Platform Project will only contain truly common components.
- Move the following component from the Platform Project (Joanna) to the Trace Project (Alex A.), including updates to the TPTP Project Matrix (see Clean-up the TPTP committer lists and project matrix.), Bugzilla Products, and Bugzilla/CVS access rights:
- Java Profiler Agent
- Trace Views
- PoG Lead: One person leading the effort different from the Trace Project lead (e.g. Chris or Mikhail). Eugene would represent IBM to evaluate quality and review requirements. Will be discussed on Wednesday's PMC call.
- ToG Lead: One person leading the effort different from the Test Project lead. Will be discussed on Wednesday's PMC call
- WTP/TPTP EPP packaging:
- Joel will discuss on the Wednesday's PMC call to effort to package all of the TPTP components.
- Mikhail will cover for Alex A. this week and report to the PMC on Wednesday's call.
- How much extra testing?
- Weekly smoke testing.
- Posting weekly/iteration test results.
Action Items
- Joanna: Communicate the limitations of the deferred I6 critical/blocker defects to the IBM consuming products impacted by these regressions.
- Joanna: Move the following component from the Platform Project (Joanna) to the Trace Project (Alex A.), including updates to the TPTP Project Matrix (see Clean-up the TPTP committer lists and project matrix.), Bugzilla Products, and Bugzilla/CVS access rights:
- Java Profiler Agent
- Trace Views
- Joel to confirm the effort to package all of the TPTP components in the WTP/TPTP EPP packaging.