Notice: This Wiki is now read only and edits are no longer possible. Please see: https://gitlab.eclipse.org/eclipsefdn/helpdesk/-/wikis/Wiki-shutdown-plan for the plan.
TPTP-Monitoring-Tools-20080311
Attendees
- Present:
- Alex Nan
- Rohit Shetty
- Hariharan Narayanan
- Yasuhisa Gotoh
- Richard Yun Song Huang
4.5
- progress has been made on reducing defect back log but there are still open outstanding defects
- defects have slipped: some have pending changes or require build changes or require more investigation
- PII and API freeze are end of i6
- TVT and enablement test case due date has changed to Feb 19th, 2008
- Alex
- fixed bug 204322, bug 212753, bug 149920
- progress on bug 220866 which turns actually out to be more complicated then initially thought
- Rohit
- has been working on updating the failing i5 AGR test cases bug 219266, bug 219265
- covered also part of Gotoh-san's tests bug 219266
- bug 164039 build changes are still not ready, Kendric promised to be done by tomorrow's PMC meeting
- the additional LTA plugins required in the AC won't be packaged by TPTP anymore, so we would need to documenbt how users can add and configure LTA extensions to AC
- Gotoh-san
- changes for bug 207251 checked in
- fixed bug 204742, Alex reviewed the patch
- Hari
- Hari work in progress on his remaining defects
- Richard
- working on tutorials bug 211085, bug 215474 which will be done by Thursday
- will work on bug 221987 starting Monday, Alex asked if he has sufficient time to finish it by end of week, Richard says yes
- Alex asked Richard to create a manual test for bug 221987 and is surprised that there is no test for this scenario since this is a basic scenario supported by BTM
Action items
- team to concentrate on reducing defect backlog
- Richard to address ASAP blocker bug 221987 and create a test for it
- Alex to start working on TVT/enablement tests once he has received all the UI changes info
- Gotoh-san to verify the AGR tests repaired by Rohit