WTP PMC Defect Review
Contents
WTP PMC Defect Review
As the end of a release cycle nears, WTP needs to add some governance in order to maintain stability and quality in the face of the upcoming deadline. To this end, a PMC review process will occur.
Important Note - The PMC Review is not an in depth technical accuracy review, but a general risk management analysis of possible benefits and associated risks of including a proposed fix.
How To Prepare a PMC Defect Candidate
The answers to the following bullets must be incorporated into the bugzilla entry before a defect will be considered for PMC approval:
- Explain why you believe this is a stop-ship defect. Or, if it is a "hotbug" (requested by an adopter) please document it as such.
- Is there a work-around? If so, why do you believe the work-around is insufficient?
- How has the fix been tested? Is there a test case attached to the bugzilla record? Has a JUnit Test been added?
- Give a brief technical overview. Who has reviewed this fix?
- What is the risk associated with this fix?
How To Get a PMC Defect Fix Candidate Approved
Overview of Steps Required:
- Developer fixes defect and attaches fix patch to the defect.
- Developer also adds documentation about the fix and why it is a must fix.
- Developer asks for component lead review and the component lead (or delegate) documents their review and approval.
- Component lead then:
- Puts "PMC" in the Status Whiteboard field.
- Adds hjzhang@ca.ibm.com as a CC to the bug.
- Adds the following to the pmc_approved flag with a "?". You can copy/paste the whole line in one field.
- david_williams@us.ibm.com, raghunathan.srinivasan@oracle.com, naci.dai@eteration.com, deboer@ca.ibm.com, neil.hauge@oracle.com
- This will add PMC approval flags for each PMC member and automatically send the PMC member an email.
- PMC members review and vote. A single negative vote will reject a defect and usually a minimum of two positive votes is required for approval. It will be incumbent on the PMC to do anything possible to perform reviews within 24 hours. To see if a bug is approved, the developer can watch the associated PMC approval PHP page, which will be dynamically updated.
- If approval is given, the developer may then release the code (tag with version and update map files) for a build.
- If the component lead does not get 24 hour turnaround on approvals, they should send a note to wtp-releng@eclipse.org with a link to the defect. (You must be a member of this list to send mail to it.)
PMC Members, How to vote
- Instead of using a "+1" comment, you update the "pmc_approved" flag for your email address with a "+" for approve and a "-" for reject. Once the appropriate amount of approvals is garnered, Helen will update the status whiteboard to "PMC_approved" or if need be, to "PMC_rejected". The PMC summary web pages are updated to ONLY look at the flags and not text comments.