COSMOS RELEASE SCHEDULE FOR 2007
- Iteration 1; Code Freeze 2/28. Iteration 1 complete March 05. (demo)
- Iteration 2: Complete iteration 2 by 4/16. (need i2 plan)
- Iteration 3: Complete iteration 3 by 5/28 (need i3 plan) to ship along with Europa.
Milestone/Task | Planned Start | Planned End | Actual Start | Actual End | % Complete | Comments | |
---|---|---|---|---|---|---|---|
Iteration 1-3 definition | 01/01/07 | 03/19/07 | - | - | - | on track | |
Iteration 1 demo development | 01/01/07 | 02/23/07 | - | - | - | on track |