Dali 2.0 planning
Contents
Links
Major Themes
- Extensibility
- Usability/Integration
- Spec related feature completion
- Validation
Requirements
Dali Requirements from WTP 3.0 Plan
Draft Milestone Plan (Rough guess on dates)
M1 - August 24, 2007
- Platform Extensibility enhancements
- Building with WTP and other Ganymede dependencies
M2 - October 2007
- Context and Resource model prototype (available in separate branch- jpt_2_0_exp)
M3 - November 2007
- Refactored context model complete
M4 - December 2007
- Exp branch merged with head
- Generators on Entity level ER 127337
- More extensible context model