August 15, 2012
Discussion
- (Markus) Auto-tagging from master is problematic in the milestone week
- No possibility for a controlled rebuild
- Not all committers seem to follow (or know about) the Eclipse process (lockdown rules; changes on or after test day need to be reviewed)
- Team leads should decide and stick to one of two working modes:
- Either work with integration and master branches, and only push integration in a controlled fashion
- Or work with master only, but make sure all committers follow the rules and do not commit ongoing work to master in milestone weeks after the last scheduled test build and until the milestone is released
- (John) What to do in the Git repository when bundles or features are removed
Status
Platform UI (Paul)
- Returning from vacations
- Juno SR1 status: still have open bugs for 4.2.1, will need to bump some to 4.2.2
Platform Text (Dani)
- Juno SR1 status: no further bug fixes planned so far
- bug fixing
Platform Debug (Michael Rennie / Pawel Piech)
- Vacation
Platform Ant (Michael Rennie)
- Vacation
Platform SWT (Silenio)
- Vacation
- Still investigating one issue for SR1 bug 321887
- GTK 3 patches review
- Bug fixing
Platform Releng (davidw)
- Promoted Kepler M1 +0 (congratulations and thanks!)
- Updated Build Schedule
- Prep for Juno RC1
- looking at bug 387052 for SR1
- hope to simplify unit tests soon bug 377718
JDT Core (Srikanth)
- Aug 15th & Aug 20th are public holidays in India.
- Juno SR1 status: no further bug fixes planned.
- bug fixing
- Java 8 on lower gear past 15 days and next week due to M1 and SR1 related work and vacations.
- We bid adieu to Ayushman Jain.
JDT Debug
JDT UI & Text (Dani)
- Juno SR1 status: fixed 1 remaining issue - no further fixes planned
- bug fixing
PDE (Curtis Windatt)
- One PDE UI bug being backported to SR1 - bug 386866 Translations for tracing preference page
- Bug fixing
- Sick time
Equinox (Tom Watson)
Equinox p2 (Ian Bull)
August 08, 2012
Discussion
- Should we collect status notes on a wiki?
- http://wiki.eclipse.org/Eclipse/Status_meetings
- answer was "yes" but suggested a "one page" format so always same page, easier to "watch" for changes.
- What build schedule would we like for Juno SR1 RC1? Our +0 day is 8/17 (then a week off, then RCs three Friday's in a row).
- Assume we'll be doing both 3.8.1 and 4.2.1 "in sync" (Though 4.2.1 is the official Juno SR1 deliverable).
- How to fit these two "M-builds" in with other I-builds, N-builds?
- M builds scheduled for Mondays? 10 AM, 12 AM Eastern, with rebuilds upon request?
- Decision was to move to Wednesday's 10, 12:00; always, instead of Thursday, and then schedule nothing special for RC weeks. This aligns with the 4.2.1 SR 1 Endgame Plan.
- Question was asked about how to "change history" to correct authorship of a commit. Basic answer was that changing history risks messing up others who have that branch checked out, so best to add a new commit explaining the connection to a bug, the other commit hash, and ?fixing? authorship if possible ... but, not sure any of us on call knew all details of how that all works with auto IP log (especially, if desire was to remove an author? ... though, not sure that's legitimate ... maybe if someone just added whitespace formatting or something?). [Its not clear, to me, how "authorship" could ever be "wrong"? Interesting case. ]
Status
Platform Text (Dani)
- working towards Kepler M1 (one day test pass, bug fixing, N&N)
- Juno SR1 status: no bug fixes planned so far
Platform Debug (Michael Rennie)
- Holidays
- Testing 4.3 M1
- SR1 - fixed two bugs, no additional fixes planned
Platform Ant (Michael Rennie)
- Holidays
- Testing 4.3 M1
- No fixes planned for SR1
Platform SWT (Silenio)
- Holidays
- SR1 fixes
- Reviewing GTK 3 patches
Platform Releng (davidw)
- Sim Release:
- Completed migration of repository to git.
- Converted and setup aggregation build for Kepler and Juno SR1
JDT Core (Srikanth)
- Working towards Kepler M1 (one day test pass, bug fixing, N&N)
- Nothing more planned for M1.
- Juno SR1 status: Still a few bugs being worked on.
JDT Debug
- Holidays
- Testing 4.3 M1
- SR1 - fixed two bugs, no additional fixes planned
JDT UI & Text (Dani)
- working towards Kepler M1 (one day test pass, bug fixing, N&N)
- Juno SR1 status: fixed 2 bugs - no further bug fixes planned to fix so far
PDE (Curtis Windatt)
- testing for M1
- no more fixes planned for SR1