Riena Project/Plan/1.1
< Riena Project
Revision as of 07:50, 6 April 2009 by Unnamed Poltroon (Talk) (New page: == Ramp Down == We are currently using daily builds. During M6 and M7 only bugs marked with the target milestone "1.1.0" can be fixed. No API changes after M6, no new features after M7. In...)
Ramp Down
We are currently using daily builds. During M6 and M7 only bugs marked with the target milestone "1.1.0" can be fixed. No API changes after M6, no new features after M7. In the RC phase only bugs marked P2 or higher or severity major or higher will be fixed.