Aperi Development Status Meeting 10/12/06
Revision as of 19:25, 5 October 2006 by Unnamed Poltroon (Talk)
Aperi Wiki Home Aperi Meetings Aperi Development Meetings
Dial in numbers:
Toll Free: 866-617-3597 International: 210-795-0625 Passcode: 6121165
Agenda:
- Project Leader Notes (Ted)
- Release Lead Notes (Dave)
- Status on initial contribution items:
Task | Duration | Start | Finish |
---|---|---|---|
Eclipse legal Review | 21 days | Thu 9/7/06 | Thu 10/05/06 |
Load code into cvs at Eclipse | 1 day | Fri 10/06/06 | Fri 10/06/06 |
Contribution downloadable in Eclipse cvs | 0 days | Fri 10/06/06 | Fri 10/06/06 |
Build instructions - Eclipse cvs | 5 days | Mon 10/09/06 | Fri 10/13/06 |
- Updated Schedule
- Phase 2:
- Design
- Implementation
- Test
- Smoke Test
- ID
- Derby issues
- Action Items
Item | Owner | Target | Status |
---|---|---|---|
Third Party Dependency Questionnaire | Helen | 09/28/06 | Questionnaires submitted 9/6. - Eclipse has started the review. Checking with Eclipse for status and a possible target end date. |
NEW: Performance Issues | Hans | 10/5/06 | Aggregate all performance issues in one wiki page |
NEW: Bug clean up | Dave | 10/13/06 | Figure out what to do with the remaining Aperi initial contribution bugs. Either fix or move to Bugzilla. |
- Other:
- Eclipse Summit Items Items updated in the document.
- Possible alternative meeting times.
- Meeting time conflict on 10/12, 11/9, and 12/7.