Difference between revisions of "Callisto Plan Summary"
m (→RC2 (9-May)) |
(add platform documentation builds (rc6,rc7)) |
||
Line 32: | Line 32: | ||
=== RC4 (2 -Jun)=== | === RC4 (2 -Jun)=== | ||
− | * 26-May - Platform ( | + | * 26-May - Platform (RC6) |
* 29-May - CDT (RC1), DTP(RC4), EMF (RCx, none planned), GEF (RC4), VE (RCx, none planned) | * 29-May - CDT (RC1), DTP(RC4), EMF (RCx, none planned), GEF (RC4), VE (RCx, none planned) | ||
* 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4) | * 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4) | ||
Line 39: | Line 39: | ||
=== RC5 (22-Jun)=== | === RC5 (22-Jun)=== | ||
− | * | + | * 2-Jun - Platform (RC7) |
* 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned) | * 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned) | ||
* 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5) | * 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5) |
Revision as of 08:39, 17 May 2006
This is summary table of the Callisto Plan
The primary purpose of this summary is to provide one place to see the correlations of the Callisto release candiate names and dates and the participating projects release candidate names and dates. The participating projects may update this page to reflect current status and plans.
Contents
RC1a (25-Apr)
- 14-Apr - Platform (RC1a)
- 19-Apr - CDT, DTP(RC1), EMF (RC1) , GEF (RC0), VE (M3)
- 21-Apr - BIRT (RC0), GMF (RC0), TPTP (i2), WTP (RC1a)
- 25-Apr - admin, mirror propagation
RC2 (9-May)
- 28-Apr - Platform (RC2)
- 3-May - CDT (RC0), DTP(RC2), EMF (RC2a) , GEF (RC2), VE (M3)
- 5-May - BIRT(RC2), GMF (RC2), TPTP (RC2), WTP (RC2)
- 9-May - admin, mirror propagation
RC3 (23-May)
- 12-May - Platform (RC4)
- 17-May - CDT (RC0), DTP(RC3), EMF (RC4), GEF (RC3), VE (RC1)
- 19-May - BIRT(RC3), GMF (RC3), TPTP (RC2), WTP (RC3)
- 23-May - admin, mirror propagation
RC4 (2 -Jun)
- 26-May - Platform (RC6)
- 29-May - CDT (RC1), DTP(RC4), EMF (RCx, none planned), GEF (RC4), VE (RCx, none planned)
- 31-May - BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
- 2 -June - admin, mirror propagation
RC5 (22-Jun)
- 2-Jun - Platform (RC7)
- 19-Jun - CDT (RC1) , DTP(RC4 planned, RC5 if needed), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
- 20-Jun - BIRT(RC5), GMF (RC5), TPTP (RC5), WTP (RC5)
- 22-Jun - admin, mirror propagation
RC6 (30-Jun)
- 28-Jun - Platform (RCx, none planned)
- 28-Jun - CDT (RC2, if needed) , DTP(RCx, none planned), EMF (RCx, none planned), GEF (RC5), VE (RCx, none planned)
- 28-Jun - BIRT (RC6), GMF (RC6), TPTP (RC6), WTP (RC6)
- 30-Jun - admin, mirror propagation